Permit: TR-UTL-0625-00892
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
1169 N WINSTEL BL
Address NEW:
1169 N WINSTEL BL
Apply Date:
06/04/2025
Applicant:
Blair Montello
Description:
P.099107 (KAHNA) - BORE 432’ & TRENCH 19’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (7) HANDHOLES & PEDESTALS. OVERLASH 1,218’ OF AERIAL FIBER CABLE. 9/2/25- RENEWAL FOR 60 DAYS AS OF 9/23/25. NEW EXPIRATION DATE 10/23/25.
Permit Reviews
Permit Number - TR-UTL-0625-00892
Permit Status: Complete
Permit Description: P.099107 (KAHNA) - BORE 432’ & TRENCH 19’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (7) HANDHOLES & PEDESTALS. OVERLASH 1,218’ OF AERIAL FIBER CABLE.
9/2/25- RENEWAL FOR 60 DAYS AS OF 9/23/25. NEW EXPIRATION DATE 10/23/25.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/04/2025 | RIGHT-OF-WAY REVIEW v.1 | 06/05/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0625-00892
Permit Status: Complete
Permit Description: P.099107 (KAHNA) - BORE 432’ & TRENCH 19’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (7) HANDHOLES & PEDESTALS. OVERLASH 1,218’ OF AERIAL FIBER CABLE.
9/2/25- RENEWAL FOR 60 DAYS AS OF 9/23/25. NEW EXPIRATION DATE 10/23/25.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 06/04/2025 | BUS STOP/ ROUTE |
| 06/04/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 06/04/2025 | Traffic Control set-up approved between 7AM - 5PM |
| 06/04/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 06/04/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0625-00892
Permit Description: P.099107 (KAHNA) - BORE 432’ & TRENCH 19’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (7) HANDHOLES & PEDESTALS. OVERLASH 1,218’ OF AERIAL FIBER CABLE.
9/2/25- RENEWAL FOR 60 DAYS AS OF 9/23/25. NEW EXPIRATION DATE 10/23/25.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 10/01/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 10/01/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 10/01/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 10/01/2025 | TRSP - ROW - Final | Passed |