Permit: TR-UTL-0624-01149
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
4220 S PARK AV
Address NEW:
4220 S PARK AV
Apply Date:
06/14/2024
Applicant:
Cox Communications
Description:
PRJ272313-1: Cox to overlash 519' to existing aerial, trench 8' and bore 78' to install CATV conduit and place vault for system tie.
Permit Reviews
Permit Number - TR-UTL-0624-01149
Permit Status: Complete
Permit Description: PRJ272313-1: Cox to overlash 519' to existing aerial, trench 8' and bore 78' to install CATV conduit and place vault for system tie.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/17/2024 | RIGHT-OF-WAY REVIEW v.1 | 06/18/2024 | REQUIRES RESUBMIT |
| 06/24/2024 | RIGHT-OF-WAY REVIEW v.2 | 06/25/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0624-01149
Permit Status: Complete
Permit Description: PRJ272313-1: Cox to overlash 519' to existing aerial, trench 8' and bore 78' to install CATV conduit and place vault for system tie.
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 06/17/2024 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 06/17/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0624-01149
Permit Description: PRJ272313-1: Cox to overlash 519' to existing aerial, trench 8' and bore 78' to install CATV conduit and place vault for system tie.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 08/23/2024 | TRSP - ROW - AERIAL INSTALLATION | Passed | ||
| 08/23/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 09/11/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 09/27/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
| 10/16/2024 | TRSP - ROW - Final/Close-Out | Passed |