Permit: TR-UTL-0624-01116
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
6166 E DIABLO SUNRISE RD
Address NEW:
6166 E DIABLO SUNRISE RD
Apply Date:
06/05/2024
Applicant:
JUAN PEREZ
Description:
Excavating a 29'X3' trench at 6166 E DIABLO SUNRISE RD to replace gas line service in row in asphalt and dirt. Trench will be located approx 10' to the east of the property p/l at the northeast corner .
Permit Reviews
Permit Number - TR-UTL-0624-01116
Permit Status: Complete
Permit Description: Excavating a 29'X3' trench at 6166 E DIABLO SUNRISE RD to replace gas line service in row in asphalt and dirt. Trench will be located approx 10' to the east of the property p/l at the northeast corner .
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/05/2024 | RIGHT-OF-WAY REVIEW v.1 | 06/05/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0624-01116
Permit Status: Complete
Permit Description: Excavating a 29'X3' trench at 6166 E DIABLO SUNRISE RD to replace gas line service in row in asphalt and dirt. Trench will be located approx 10' to the east of the property p/l at the northeast corner .
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 06/05/2024 | PAVING |
| 06/05/2024 | Traffic Control set-up approved between 7AM - 5PM |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-0624-01116
Permite Description: Excavating a 29'X3' trench at 6166 E DIABLO SUNRISE RD to replace gas line service in row in asphalt and dirt. Trench will be located approx 10' to the east of the property p/l at the northeast corner .
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2024 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Re-inspection required | no density tests given. site completed |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0624-01116
Permit Description: Excavating a 29'X3' trench at 6166 E DIABLO SUNRISE RD to replace gas line service in row in asphalt and dirt. Trench will be located approx 10' to the east of the property p/l at the northeast corner .
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/12/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | crews are going to try and bore under roadway to install new service line. if trenching is done there will be no surface treatment required due to existing roadway conditions. a t top patch will be suffice. | |
| 07/25/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | ||
| 07/25/2024 | TRSP - ROW - Notice of Completion | Passed | ||
| 01/27/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | Work was completed over six months ago and a final inspection was already passed. This permit is old and expired and needs to be closed out. |