Permit: TR-UTL-0624-01098
Permit Details
Apply Date:
06/04/2024
Applicant:
DOONE BAKER
Description:
P.235785 - Access of ex HH 19659 for splicing/placing, place (1) HH & (1) ped, dig (3) pits, bore 108' and trench 69'
Permit Reviews
Permit Number - TR-UTL-0624-01098
Permit Status: Complete
Permit Description: P.235785 - Access of ex HH 19659 for splicing/placing, place (1) HH & (1) ped, dig (3) pits, bore 108' and trench 69'
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/04/2024 | RIGHT-OF-WAY REVIEW v.1 | 06/05/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0624-01098
Permit Status: Complete
Permit Description: P.235785 - Access of ex HH 19659 for splicing/placing, place (1) HH & (1) ped, dig (3) pits, bore 108' and trench 69'
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
06/04/2024 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
06/04/2024 | Traffic control set-up approved between 9AM - 3:30PM |
06/04/2024 | Pavement Patch type Shall Be in conformance to the current edition of the City of Tucson Public Utility Administrative Manual. |
06/04/2024 | PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0624-01098
Permit Description: P.235785 - Access of ex HH 19659 for splicing/placing, place (1) HH & (1) ped, dig (3) pits, bore 108' and trench 69'
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/14/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
09/19/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
09/19/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | ||
09/19/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
09/19/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
09/19/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
09/19/2024 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | ||
09/19/2024 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed |