Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Apply Date:
06/30/2023
Applicant:
Cox Communications
Description:
PRJ253247-3 From TEP Pole on SE corner of E Tanque Verde Rd and N Camino Pio Decimo, head W and begin ~ 745' aerial overlash. Head N and continue ~135' aerial overlash on to property. Head W and continue ~850' aerial overlash. Riser down pole, place 4x4' pot hole and new 3x4' vault. Head N and pull through ~150' of 144ct fiber through existing conduit. Place 4x4' pot hole and new 3x4' vault. Tie in. Head W and continue ~1790' aerial overlash. Riser down pole, Remove and replace existing vault with 3x4' vault. Tie in.

Permit Reviews

Permit Number - TR-UTL-0623-01922
Permit Status: Complete
Permit Description: PRJ253247-3 From TEP Pole on SE corner of E Tanque Verde Rd and N Camino Pio Decimo, head W and begin ~ 745' aerial overlash. Head N and continue ~135' aerial overlash on to property. Head W and continue ~850' aerial overlash. Riser down pole, place 4x4' pot hole and new 3x4' vault. Head N and pull through ~150' of 144ct fiber through existing conduit. Place 4x4' pot hole and new 3x4' vault. Tie in. Head W and continue ~1790' aerial overlash. Riser down pole, Remove and replace existing vault with 3x4' vault. Tie in.
Start Date Submittal Complete Date Status  
06/30/2023 RIGHT-OF-WAY REVIEW v.1 07/07/2023 REQUIRES RESUBMIT Review Details
07/19/2023 RIGHT-OF-WAY REVIEW v.2 07/20/2023 APPROVED Review Details

Conditions

Permit Number - TR-UTL-0623-01922
Permit Status: Complete
Permit Description: PRJ253247-3 From TEP Pole on SE corner of E Tanque Verde Rd and N Camino Pio Decimo, head W and begin ~ 745' aerial overlash. Head N and continue ~135' aerial overlash on to property. Head W and continue ~850' aerial overlash. Riser down pole, place 4x4' pot hole and new 3x4' vault. Head N and pull through ~150' of 144ct fiber through existing conduit. Place 4x4' pot hole and new 3x4' vault. Tie in. Head W and continue ~1790' aerial overlash. Riser down pole, Remove and replace existing vault with 3x4' vault. Tie in.
Date Description Comments
06/30/2023 BUS STOP IN AREA, CONTACT SUN TRAN DISPATCH AT 520-206-8934 AND/OR BEA PAULUS AT 520-206-8826 AT LEAST 48-BUISNESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
06/30/2023 Traffic control set-up approved between 9AM - 3:30PM
06/30/2023 PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D.

Outstanding Inspections

Permit Status: Complete
Permit Number: TR-UTL-0623-01922
Permite Description: PRJ253247-3 From TEP Pole on SE corner of E Tanque Verde Rd and N Camino Pio Decimo, head W and begin ~ 745' aerial overlash. Head N and continue ~135' aerial overlash on to property. Head W and continue ~850' aerial overlash. Riser down pole, place 4x4' pot hole and new 3x4' vault. Head N and pull through ~150' of 144ct fiber through existing conduit. Place 4x4' pot hole and new 3x4' vault. Tie in. Head W and continue ~1790' aerial overlash. Riser down pole, Remove and replace existing vault with 3x4' vault. Tie in.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/16/2023 TRSP - ROW - Recurring N/A Complete (Recurring)

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0623-01922
Permit Description: PRJ253247-3 From TEP Pole on SE corner of E Tanque Verde Rd and N Camino Pio Decimo, head W and begin ~ 745' aerial overlash. Head N and continue ~135' aerial overlash on to property. Head W and continue ~850' aerial overlash. Riser down pole, place 4x4' pot hole and new 3x4' vault. Head N and pull through ~150' of 144ct fiber through existing conduit. Place 4x4' pot hole and new 3x4' vault. Tie in. Head W and continue ~1790' aerial overlash. Riser down pole, Remove and replace existing vault with 3x4' vault. Tie in.
Total Completed Inspections - 2
Date Description Inspector Results Comments
10/12/2023 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
12/12/2023 TRSP - ROW - Final/Close-Out Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
PRJ253247-3_8VER1-SOUTHWEST-PHOENIX-PONO-2022_2390 N CAMINO PIO DECIMO_TCP_REV1 (1)_V2.PDF DOCUMENTS VIEW
PRJ253247-3 SKETCH_V1.PDF DOCUMENTS VIEW