Permit: TR-UTL-0526-00891
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
2401 S HOUGHTON RD
Address NEW:
2401 S HOUGHTON RD
Apply Date:
05/27/2026
Applicant:
Esteban Vega - Desert Barricades
Description:
Continuation of work on permit # TR-UTL-1225-02053. WO T23050, T74431. TEP will be removing 5 poles along the East side of Houghton Road from Sahuaro Baptist Church driveway to TEP Spanish Trail Substation. (DTM - NIGHT WORK APPROVED ONLY for Lane Closures on Houghton Road- DTM 5/28/2026)
Permit Reviews
Permit Number - TR-UTL-0526-00891
Permit Status: Complete
Permit Description: Continuation of work on permit # TR-UTL-1225-02053. WO T23050, T74431. TEP will be removing 5 poles along the East side of Houghton Road from Sahuaro Baptist Church driveway to TEP Spanish Trail Substation.
(DTM - NIGHT WORK APPROVED ONLY for Lane Closures on Houghton Road- DTM 5/28/2026)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/27/2026 | RIGHT-OF-WAY REVIEW v.1 | 05/28/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0526-00891
Permit Status: Complete
Permit Description: Continuation of work on permit # TR-UTL-1225-02053. WO T23050, T74431. TEP will be removing 5 poles along the East side of Houghton Road from Sahuaro Baptist Church driveway to TEP Spanish Trail Substation.
(DTM - NIGHT WORK APPROVED ONLY for Lane Closures on Houghton Road- DTM 5/28/2026)
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 05/28/2026 | The following extended traffic control set-up times were approved: Approved for Night Work ONLY 8pm to 5 am |
| 05/28/2026 | **Pre-Activity Meeting w/Inspections **Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 05/28/2026 | Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk |
| 05/28/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 05/28/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 05/28/2026 | Approved Temporary Noise Exemption required prior to Night work being performed within the City of Tucson Right of Way.. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0526-00891
Permit Description: Continuation of work on permit # TR-UTL-1225-02053. WO T23050, T74431. TEP will be removing 5 poles along the East side of Houghton Road from Sahuaro Baptist Church driveway to TEP Spanish Trail Substation.
(DTM - NIGHT WORK APPROVED ONLY for Lane Closures on Houghton Road- DTM 5/28/2026)
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | all barricades removed from site | |
| 08/14/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | covered pre activity inspection on previous permit | |
| 08/14/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | New poles are in place, shoulder landscape area is completely backfilled | |
| 08/14/2026 | TRSP - ROW - Final | Passed | all pole installation has been completed, traffic control devices removed from site, approved |