Permit: TR-UTL-0526-00856
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
610 W SPEEDWAY BL
Address NEW:
610 W SPEEDWAY BL
Apply Date:
05/20/2026
Applicant:
Brittany West
Description:
Tie point will be existing aerial splice case on utility pole. Overlash 280' of 288ct fiber over 4 spans. Overlash 635' of 288ct fiber over 7 spans. Place 745' of new strand over 5 spans. Lash 745' of 288ct fiber over 5 spans. Place new riser.Bore 170' of 2" conduit at a depth of 3', run 170' of 288ct. Place new vault. Bore 670' of 2" conduit at a depth of 3', run 670' of 288ct. Place new vault. Bore 780' of 2" conduit at a depth of 3', run 780' of 288ct. Place new vault. Bore 560' of 2" conduit at a depth of 3', run 560' of 288ct. Place new vault. Bore 240' of 2" conduit at a depth of 3', run 240' of 288ct. Place new riser. Place 790' of new strand over 8 spans. Lash 745' of 288ct fiber over 8 spans.
Permit Reviews
Permit Number - TR-UTL-0526-00856
Permit Status: Complete
Permit Description: Tie point will be existing aerial splice case on utility pole. Overlash 280' of 288ct fiber over 4 spans. Overlash 635' of 288ct fiber over 7 spans. Place 745' of new strand over 5 spans. Lash 745' of 288ct fiber over 5 spans. Place new riser.Bore 170' of 2" conduit at a depth of 3', run 170' of 288ct. Place new vault. Bore 670' of 2" conduit at a depth of 3', run 670' of 288ct. Place new vault. Bore 780' of 2" conduit at a depth of 3', run 780' of 288ct. Place new vault. Bore 560' of 2" conduit at a depth of 3', run 560' of 288ct. Place new vault. Bore 240' of 2" conduit at a depth of 3', run 240' of 288ct. Place new riser. Place 790' of new strand over 8 spans. Lash 745' of 288ct fiber over 8 spans.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/20/2026 | RIGHT-OF-WAY REVIEW v.1 | 06/04/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0526-00856
Permit Status: Complete
Permit Description: Tie point will be existing aerial splice case on utility pole. Overlash 280' of 288ct fiber over 4 spans. Overlash 635' of 288ct fiber over 7 spans. Place 745' of new strand over 5 spans. Lash 745' of 288ct fiber over 5 spans. Place new riser.Bore 170' of 2" conduit at a depth of 3', run 170' of 288ct. Place new vault. Bore 670' of 2" conduit at a depth of 3', run 670' of 288ct. Place new vault. Bore 780' of 2" conduit at a depth of 3', run 780' of 288ct. Place new vault. Bore 560' of 2" conduit at a depth of 3', run 560' of 288ct. Place new vault. Bore 240' of 2" conduit at a depth of 3', run 240' of 288ct. Place new riser. Place 790' of new strand over 8 spans. Lash 745' of 288ct fiber over 8 spans.
Total Outstanding Activity Conditions - 11
| Date | Name |
|---|---|
| 05/22/2026 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 05/22/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 05/22/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 05/22/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 05/22/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 06/01/2026 | Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign. |
| 06/01/2026 | Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk - The contractor shall restore all disturbed pavement in accordance with the City of Tucson Standard Specifications for Public Improvements and applicable standard details. All pavement patches shall match the existing pavement section and surface condition. The contractor shall maintain all temporary patches in a safe and drivable condition until permanent restoration is completed. Any settlement, cracking, or pavement failure within the patched area shall be repaired by the contractor at no cost to the City for the duration of the warranty period All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |
| 06/01/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 06/01/2026 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 06/01/2026 | Rolling Traffic Control Closures Law Enforcement Point Control Required at All crossing of Signalized or Major Intersections Rolling Closure to Require Cone placement for extended Static Work Pre-Warning Signing to include Road Work Ahead, w/Right Lane Closed Ahead on Truck for Stand by Flagman to be used for Side roads for Static Work locations. Rolling shadow traffic control closures not to exceed 1 hrs in a single location, with on site flaggers for right of way with less than 2 travel lanes in each direction. Closure to exceed 1 hrs will require full traffic control setups based on road configuration. |
| 06/01/2026 | Approved Temporary Noise Exemption required prior to Night work being performed within the City of Tucson Right of Way.. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0526-00856
Permit Description: Tie point will be existing aerial splice case on utility pole. Overlash 280' of 288ct fiber over 4 spans. Overlash 635' of 288ct fiber over 7 spans. Place 745' of new strand over 5 spans. Lash 745' of 288ct fiber over 5 spans. Place new riser.Bore 170' of 2" conduit at a depth of 3', run 170' of 288ct. Place new vault. Bore 670' of 2" conduit at a depth of 3', run 670' of 288ct. Place new vault. Bore 780' of 2" conduit at a depth of 3', run 780' of 288ct. Place new vault. Bore 560' of 2" conduit at a depth of 3', run 560' of 288ct. Place new vault. Bore 240' of 2" conduit at a depth of 3', run 240' of 288ct. Place new riser. Place 790' of new strand over 8 spans. Lash 745' of 288ct fiber over 8 spans.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/11/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | RIGHT-OF-WAY PERMIT ACTIVITY TR-UTL-0126-00115 this is the old permit number. The current pre-con is for the new permit number. |
|
| 06/30/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | making a permanent asphalt repair to one of their temporary asphalt patches | |
| 06/25/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 06/25/2026 | TRSP - ROW - AERIAL INSTALLATION | Passed | ||
| 07/08/2026 | TRSP - ROW - Final | Passed | All work completed on this permit restoration has been completed |