Description:
P.355277B OVERBUILD BORE 1118' AND TRENCH 100' TO PLACE CONDIUT AND FIBER CABLE PLACE 103' OF AERIAL FIBER CABLE
Permit Reviews
Permit Number - TR-UTL-0526-00821
Permit Status: In review
Permit Description: P.355277B OVERBUILD
BORE 1118' AND TRENCH 100' TO PLACE CONDIUT AND FIBER CABLE
PLACE 103' OF AERIAL FIBER CABLE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/13/2026 | RIGHT-OF-WAY REVIEW v.1 | 05/20/2026 | REQUIRES RESUBMIT |
| 06/15/2026 | RIGHT-OF-WAY REVIEW v.2 | 06/15/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0526-00821
Permit Status: In review
Permit Description: P.355277B OVERBUILD
BORE 1118' AND TRENCH 100' TO PLACE CONDIUT AND FIBER CABLE
PLACE 103' OF AERIAL FIBER CABLE
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 05/18/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 05/19/2026 | Alley Restrictions Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced |
| 05/19/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 05/19/2026 | Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 05/19/2026 | Private Property Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property. |