Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
2813 N SWAN RD
Address NEW:
2813 N SWAN RD
Apply Date:
05/12/2026
Applicant:
Kristine Schwartz
Description:
SWG crews needs to cycle gas valves- no excavation needed. Will need TCP for safety.

Permit Reviews

Permit Number - TR-UTL-0526-00817
Permit Status: Complete
Permit Description: SWG crews needs to cycle gas valves- no excavation needed. Will need TCP for safety.
Start Date Submittal Complete Date Status  
05/26/2026 RIGHT-OF-WAY REVIEW v.2 05/27/2026 APPROVED Review Details
05/12/2026 RIGHT-OF-WAY REVIEW v.1 05/18/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0526-00817
Permit Status: Complete
Permit Description: SWG crews needs to cycle gas valves- no excavation needed. Will need TCP for safety.
Total Outstanding Activity Conditions - 7
Date Name
05/13/2026 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
05/13/2026 PAVEMENT MORATORIUM: ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES.
05/13/2026 Traffic control set-up approved between 9AM - 3:30PM
05/27/2026 Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
05/27/2026 Rolling shadow traffic control closures not to exceed 2 hrs in a single location, with on site flaggers for right of way with less than 2 travel lanes in each direction. Closure to exceed 2 hrs will require full traffic control setups based on road configuration.
05/27/2026 Rolling Traffic Control Closures Law Enforcement Point Control Required at All crossing of Signalized or Major Intersections Rolling Closure to Require Cone placement for extended Static Work Pre-Warning Signing to include Road Work Ahead, w/Right Lane Closed Ahead on Truck for Stand by Flagman to be used for Side roads for Static Work locations
05/27/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0526-00817
Permit Description: SWG crews needs to cycle gas valves- no excavation needed. Will need TCP for safety.
Total Completed Inspections - 3
Date Description Inspector Results Comments
06/01/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
07/01/2026 TRSP - ROW - Barricade - Setup/Routine Passed
07/01/2026 TRSP - ROW - Final Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
2813 N SWAN RD SHADOW TRUCK- REVISED_V1.PDF DOCUMENTS VIEW