Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Apply Date:
05/11/2026
Applicant:
Brittany West
Description:
starting phase 2 at the end of phase 1. Hang 2,825ft of new strand and new 144ct fiber.this is part 2 of phase 2. hang 2,415ft of new strand and 144ct fiber.

Permit Reviews

Permit Number - TR-UTL-0526-00800
Permit Status: Complete
Permit Description: starting phase 2 at the end of phase 1. Hang 2,825ft of new strand and new 144ct fiber.this is part 2 of phase 2. hang 2,415ft of new strand and 144ct fiber.
Start Date Submittal Complete Date Status  
05/11/2026 RIGHT-OF-WAY REVIEW v.1 06/11/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0526-00800
Permit Status: Complete
Permit Description: starting phase 2 at the end of phase 1. Hang 2,825ft of new strand and new 144ct fiber.this is part 2 of phase 2. hang 2,415ft of new strand and 144ct fiber.
Total Outstanding Activity Conditions - 8
Date Name
05/22/2026 This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to the Historic Preservation Office, City of Tucson, PO BOX 27210, Tucson AZ 85726...***Please contact Historic Preservation Office at PDSDHistoric@tucsonaz.gov.
05/22/2026 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
05/22/2026 ROW Permit is only allowed for work within City of Tucson Right of Way.
05/22/2026 Approved for Work within City of Tucson Right of Way Only. Pima Couty permits will be required for work in and Traffic Control within Pima ROW
05/22/2026 Traffic control set-up approved between 9AM - 3:30PM
05/22/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
05/22/2026 PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
06/03/2026 Flaggers shall remain on sidewalk only. Flaggers shall not be placed on arterial or collector streets such as Irvington Rd and Mission. Police point control required when crossing Irvington.

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0526-00800
Permit Description: starting phase 2 at the end of phase 1. Hang 2,825ft of new strand and new 144ct fiber.this is part 2 of phase 2. hang 2,415ft of new strand and 144ct fiber.
Total Completed Inspections - 4
Date Description Inspector Results Comments
07/21/2026 TRSP - ROW - Barricade - Setup/Routine Passed
07/21/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
07/21/2026 TRSP - ROW - AERIAL INSTALLATION Passed
07/21/2026 TRSP - ROW - Final Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
JB0002329112_PERMIT MAP_PHASE 2 PART 1_V1.PDF DOCUMENTS VIEW
JB0002329112_PERMIT MAP_PHASE 2 PART 2_V1.PDF DOCUMENTS VIEW
TCP_V1.PDF DOCUMENTS VIEW