Permit: TR-UTL-0426-00753
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW) - Utility
Address:
2575 E MENOR SV
Address NEW:
2575 E MENOR SV
Apply Date:
04/30/2026
Applicant:
Austin Eslick
Description:
T139761 - Remove (1) TEP pole. Install (6) TEP poles, (2) guy anchors, OH conductors & OH attachments. Replace (16) TEP poles, (4) guy anchors, OH conductors & OH attachments. 2'x2' & 4'x4' pole excavations. Possible sidewalk impact at pole 235, 236, 237 & 238. Continuation of Permit TR-UTL-1025-01829
Permit Reviews
Permit Number - TR-UTL-0426-00753
Permit Status: Needs resubmittal
Permit Description: T139761 - Remove (1) TEP pole. Install (6) TEP poles, (2) guy anchors, OH conductors & OH attachments. Replace (16) TEP poles, (4) guy anchors, OH conductors & OH attachments. 2'x2' & 4'x4' pole excavations. Possible sidewalk impact at pole 235, 236, 237 & 238. Continuation of Permit TR-UTL-1025-01829
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/30/2026 | RIGHT-OF-WAY REVIEW v.1 | 05/08/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0426-00753
Permit Status: Needs resubmittal
Permit Description: T139761 - Remove (1) TEP pole. Install (6) TEP poles, (2) guy anchors, OH conductors & OH attachments. Replace (16) TEP poles, (4) guy anchors, OH conductors & OH attachments. 2'x2' & 4'x4' pole excavations. Possible sidewalk impact at pole 235, 236, 237 & 238. Continuation of Permit TR-UTL-1025-01829
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 05/07/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 05/07/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 05/07/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 05/08/2026 | Excavation - All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |
| 05/08/2026 | Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk. |
| 05/08/2026 | Stored materials, including utility poles, shall maintain a continuous ADA-compliant pedestrian route and shall not encroach into bicycle facilities or pedestrian travel ways unless specifically authorized by the approved TCP. Any temporary obstruction must include advance warning devices, barricades, and nighttime visibility measures. |
| 05/08/2026 | The contractor shall not block driveways or restrict resident access without prior notification and shall coordinate directly with affected property owners as necessary |
| 05/08/2026 | This permit authorizes work within the City right-of-way only. Any work outside the public right-of-way shall require authorization from the appropriate property owner and/or permitting agency prior to construction. |