Permit: TR-UTL-0426-00706
Permit Details
Apply Date:
04/23/2026
Applicant:
Tucson Electric Power
Description:
WO T134837 - Replacing equipment on an existing pole
Permit Reviews
Permit Number - TR-UTL-0426-00706
Permit Status: Complete
Permit Description: WO T134837 - Replacing equipment on an existing pole
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/14/2026 | RIGHT-OF-WAY REVIEW v.3 | 05/15/2026 | APPROVED |
| 04/29/2026 | RIGHT-OF-WAY REVIEW v.2 | 05/13/2026 | REQUIRES RESUBMIT |
| 04/23/2026 | RIGHT-OF-WAY REVIEW v.1 | 04/23/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0426-00706
Permit Status: Complete
Permit Description: WO T134837 - Replacing equipment on an existing pole
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 04/23/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 04/23/2026 | PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTAINED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 04/23/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 04/23/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 04/23/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 05/15/2026 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0426-00706
Permit Description: WO T134837 - Replacing equipment on an existing pole
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/22/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | The poll has been put in place. The majority of the work will be on the pole replacing parts. |