Permit: TR-UTL-0426-00688
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
5495 E FORT LOWELL RD
Address NEW:
5495 E FORT LOWELL RD
Apply Date:
04/21/2026
Applicant:
Brittany West
Description:
replacing existing rhino cabinet with a node ped and vault. trench along proposed path fir 140ft at a depth of 36 inches. bore along proposed path for 110ft at a depth of 36 inches. Request for 60 Day Renewal as of 06/04/2026
Permit Reviews
Permit Number - TR-UTL-0426-00688
Permit Status: Complete
Permit Description: replacing existing rhino cabinet with a node ped and vault. trench along proposed path fir 140ft at a depth of 36 inches. bore along proposed path for 110ft at a depth of 36 inches.
Request for 60 Day Renewal as of 06/04/2026
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/22/2026 | RIGHT-OF-WAY REVIEW v.2 | 04/23/2026 | APPROVED |
| 04/21/2026 | RIGHT-OF-WAY REVIEW v.1 | 04/22/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0426-00688
Permit Status: Complete
Permit Description: replacing existing rhino cabinet with a node ped and vault. trench along proposed path fir 140ft at a depth of 36 inches. bore along proposed path for 110ft at a depth of 36 inches.
Request for 60 Day Renewal as of 06/04/2026
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 04/21/2026 | This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Jodie Brown at Jodie.Brown@tucsonaz.gov with any questions. |
| 04/21/2026 | Notify in writing at least 5 working days before work begins, any businesses, residences and public transit routes affected by your temporary traffic control. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 04/21/2026 | PAVEMENT MORATORIUM: ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
| 04/21/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 04/21/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 04/22/2026 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign. |
| 04/22/2026 | Private Property Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property. |
| 04/22/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0426-00688
Permit Description: replacing existing rhino cabinet with a node ped and vault. trench along proposed path fir 140ft at a depth of 36 inches. bore along proposed path for 110ft at a depth of 36 inches.
Request for 60 Day Renewal as of 06/04/2026
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/17/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 07/31/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 07/31/2026 | TRSP - ROW - Final | Passed |