Permit: TR-UTL-0426-00662
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
2802 N FLOWING WELLS RD
Address NEW:
2802 N FLOWING WELLS RD
Apply Date:
04/14/2026
Applicant:
Angie Covarrubias
Description:
CONTINUATION PERMIT FOR TR-UTL-1025-01756 - NO CHANGES/UPDATES TO ORIGINAL PERMIT, WILL NEED THE SAME CONDITIONS: This franchise project involves the replacement of predominantly 5,182 feet of 1960's vintage 2" steel and 1087 feet of 1987-2021 PE8000/8100 main along with associated service lines. The project is being initiated by the City of Tucson under Job Number U-2024-033. The proposed improvements begin at the intersection of Flowing Wells and Miracle Mile and extend to the intersection of Grant Road. Scope of work includes roadway repaving, and sidewalks/ramps. COT project is scheduled to start during the first quarter of 2026. Due to the soil conditions within the project area, grade cuts will reach depths greater than 3 feet deep, placing the existing pipeline in direct conflict with the proposed grading. In total, the project will involve the installation of 6,063feet of 4" PE8400 main, 12 feet of 2" PE8400 and 14 feet of 1" PE8400 along with 1,590 feet of service line. The main installation method to be used is boring (5'x10' bore pits). 07/21/26- RENEW PERMIT FOR 90 DAYS AS OF 07/21/26 NEW EXPIRATION DATE IS 10/19/26
Permit Reviews
Permit Number - TR-UTL-0426-00662
Permit Status: Inspections
Permit Description: CONTINUATION PERMIT FOR TR-UTL-1025-01756 - NO CHANGES/UPDATES TO ORIGINAL PERMIT, WILL NEED THE SAME CONDITIONS:
This franchise project involves the replacement of predominantly 5,182 feet of 1960's vintage 2" steel and 1087 feet of 1987-2021 PE8000/8100 main along with associated service lines. The project is being initiated by the City of Tucson under Job Number U-2024-033. The proposed improvements begin at the intersection of Flowing Wells and Miracle Mile and extend to the intersection of Grant Road. Scope of work includes roadway repaving, and sidewalks/ramps. COT project is scheduled to start during the first quarter of 2026. Due to the soil conditions within the project area, grade cuts will reach depths greater than 3 feet deep, placing the existing pipeline in direct conflict with the proposed grading. In total, the project will involve the installation of 6,063feet of 4" PE8400 main, 12 feet of 2" PE8400 and 14 feet of 1" PE8400 along with 1,590 feet of service line. The main installation method to be used is boring (5'x10' bore pits).
07/21/26- RENEW PERMIT FOR 90 DAYS AS OF 07/21/26 NEW EXPIRATION DATE IS 10/19/26
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/14/2026 | RIGHT-OF-WAY REVIEW v.1 | 04/17/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0426-00662
Permit Status: Inspections
Permit Description: CONTINUATION PERMIT FOR TR-UTL-1025-01756 - NO CHANGES/UPDATES TO ORIGINAL PERMIT, WILL NEED THE SAME CONDITIONS:
This franchise project involves the replacement of predominantly 5,182 feet of 1960's vintage 2" steel and 1087 feet of 1987-2021 PE8000/8100 main along with associated service lines. The project is being initiated by the City of Tucson under Job Number U-2024-033. The proposed improvements begin at the intersection of Flowing Wells and Miracle Mile and extend to the intersection of Grant Road. Scope of work includes roadway repaving, and sidewalks/ramps. COT project is scheduled to start during the first quarter of 2026. Due to the soil conditions within the project area, grade cuts will reach depths greater than 3 feet deep, placing the existing pipeline in direct conflict with the proposed grading. In total, the project will involve the installation of 6,063feet of 4" PE8400 main, 12 feet of 2" PE8400 and 14 feet of 1" PE8400 along with 1,590 feet of service line. The main installation method to be used is boring (5'x10' bore pits).
07/21/26- RENEW PERMIT FOR 90 DAYS AS OF 07/21/26 NEW EXPIRATION DATE IS 10/19/26
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 04/21/2026 | The following extended traffic control set-up times were approved: |
| 04/21/2026 | Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 04/21/2026 | TEMPORARY NOISE EXEMPTION |
| 04/21/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 04/21/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0426-00662
Permite Description: CONTINUATION PERMIT FOR TR-UTL-1025-01756 - NO CHANGES/UPDATES TO ORIGINAL PERMIT, WILL NEED THE SAME CONDITIONS:
This franchise project involves the replacement of predominantly 5,182 feet of 1960's vintage 2" steel and 1087 feet of 1987-2021 PE8000/8100 main along with associated service lines. The project is being initiated by the City of Tucson under Job Number U-2024-033. The proposed improvements begin at the intersection of Flowing Wells and Miracle Mile and extend to the intersection of Grant Road. Scope of work includes roadway repaving, and sidewalks/ramps. COT project is scheduled to start during the first quarter of 2026. Due to the soil conditions within the project area, grade cuts will reach depths greater than 3 feet deep, placing the existing pipeline in direct conflict with the proposed grading. In total, the project will involve the installation of 6,063feet of 4" PE8400 main, 12 feet of 2" PE8400 and 14 feet of 1" PE8400 along with 1,590 feet of service line. The main installation method to be used is boring (5'x10' bore pits).
07/21/26- RENEW PERMIT FOR 90 DAYS AS OF 07/21/26 NEW EXPIRATION DATE IS 10/19/26
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/13/2026 | TRSP - ROW - Final | N/A | Re-inspection required | Work still in progress and extension of the other permit or the new permit that's getting added to this we will close this after the new permit is opened and we have the pre-construction meeting again |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0426-00662
Permit Description: CONTINUATION PERMIT FOR TR-UTL-1025-01756 - NO CHANGES/UPDATES TO ORIGINAL PERMIT, WILL NEED THE SAME CONDITIONS:
This franchise project involves the replacement of predominantly 5,182 feet of 1960's vintage 2" steel and 1087 feet of 1987-2021 PE8000/8100 main along with associated service lines. The project is being initiated by the City of Tucson under Job Number U-2024-033. The proposed improvements begin at the intersection of Flowing Wells and Miracle Mile and extend to the intersection of Grant Road. Scope of work includes roadway repaving, and sidewalks/ramps. COT project is scheduled to start during the first quarter of 2026. Due to the soil conditions within the project area, grade cuts will reach depths greater than 3 feet deep, placing the existing pipeline in direct conflict with the proposed grading. In total, the project will involve the installation of 6,063feet of 4" PE8400 main, 12 feet of 2" PE8400 and 14 feet of 1" PE8400 along with 1,590 feet of service line. The main installation method to be used is boring (5'x10' bore pits).
07/21/26- RENEW PERMIT FOR 90 DAYS AS OF 07/21/26 NEW EXPIRATION DATE IS 10/19/26
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/21/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | This is the new permit after they already exhausted their limits of the old permit for renewals, pre-con and all specs same requirements following pack standards from the previous permit revisited with the on-site supervisor everything is still the same continuing the work | |
| 07/17/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | This is the new permit after they already exhausted their limits of the old permit for renewals, pre-con and all specs same requirements following pack standards from the previous permit revisited with the on-site supervisor everything is still the same continuing the work the restoration still has not been complete completed permanent patch | |
| 10/13/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | Continuation of work final inspection will be done on renewed permit |