Permit: TR-UTL-0425-00709
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
8300 E TANQUE VERDE RD
Address NEW:
8300 E TANQUE VERDE RD
Apply Date:
04/29/2025
Applicant:
Eric Wieduwilt
Description:
PLEASE REFERENCE PERMIT TR-UTL-1124-02182. Permit was approved and issued but work did not begin in allotted time frame. Public sewer improvements. Installing 3,740lf of new sewer line and manholes along the south side of E. Tanque Verde Rd. with two sections crossing the road from the North side of E. Tanque Verde Rd. to South side of E. Tanque Verde Rd. -Workdays - Monday through Friday -Work Hours - 6am to 2pm -Work Duration - 3 months (Crossings to take 2 weeks each including patchback of asphalt) (Remainder of work on south side of E. Tanque Verde Rd. to take 2 months) -Work on south side of E. Tanque Verde Rd. to primarily use shoulder/bike lane closures as shown in TCP, right lane closure to be used only if necessary -Work crossing from north to south on both the maximum west and east ends of the project to use a combination of a right lane closure then a "football setup" to completes the crossing in a 4-step process (right lane closure for southern east bound lane, "football" for northern east bound lane the median and the southern west bound lane, right lane closure for northern west bound lane) -Nights/Variable hours of work for major crossing can be accepted in order to comply with COTDOT needs if needed
Permit Reviews
Permit Number - TR-UTL-0425-00709
Permit Status: Complete
Permit Description: PLEASE REFERENCE PERMIT TR-UTL-1124-02182. Permit was approved and issued but work did not begin in allotted time frame.
Public sewer improvements. Installing 3,740lf of new sewer line and manholes along the south side of E. Tanque Verde Rd. with two sections crossing the road from the North side of E. Tanque Verde Rd. to South side of E. Tanque Verde Rd.
-Workdays - Monday through Friday
-Work Hours - 6am to 2pm
-Work Duration - 3 months (Crossings to take 2 weeks each including patchback of asphalt) (Remainder of work on south side of E. Tanque Verde Rd. to take 2 months)
-Work on south side of E. Tanque Verde Rd. to primarily use shoulder/bike lane closures as shown in TCP, right lane closure to be used only if necessary
-Work crossing from north to south on both the maximum west and east ends of the project to use a combination of a right lane closure then a "football setup" to completes the crossing in a 4-step process (right lane closure for southern east bound lane, "football" for northern east bound lane the median and the southern west bound lane, right lane closure for northern west bound lane)
-Nights/Variable hours of work for major crossing can be accepted in order to comply with COTDOT needs if needed
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/29/2025 | RIGHT-OF-WAY REVIEW v.1 | 05/09/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0425-00709
Permit Status: Complete
Permit Description: PLEASE REFERENCE PERMIT TR-UTL-1124-02182. Permit was approved and issued but work did not begin in allotted time frame.
Public sewer improvements. Installing 3,740lf of new sewer line and manholes along the south side of E. Tanque Verde Rd. with two sections crossing the road from the North side of E. Tanque Verde Rd. to South side of E. Tanque Verde Rd.
-Workdays - Monday through Friday
-Work Hours - 6am to 2pm
-Work Duration - 3 months (Crossings to take 2 weeks each including patchback of asphalt) (Remainder of work on south side of E. Tanque Verde Rd. to take 2 months)
-Work on south side of E. Tanque Verde Rd. to primarily use shoulder/bike lane closures as shown in TCP, right lane closure to be used only if necessary
-Work crossing from north to south on both the maximum west and east ends of the project to use a combination of a right lane closure then a "football setup" to completes the crossing in a 4-step process (right lane closure for southern east bound lane, "football" for northern east bound lane the median and the southern west bound lane, right lane closure for northern west bound lane)
-Nights/Variable hours of work for major crossing can be accepted in order to comply with COTDOT needs if needed
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 04/30/2025 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 04/30/2025 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0425-00709
Permit Description: PLEASE REFERENCE PERMIT TR-UTL-1124-02182. Permit was approved and issued but work did not begin in allotted time frame.
Public sewer improvements. Installing 3,740lf of new sewer line and manholes along the south side of E. Tanque Verde Rd. with two sections crossing the road from the North side of E. Tanque Verde Rd. to South side of E. Tanque Verde Rd.
-Workdays - Monday through Friday
-Work Hours - 6am to 2pm
-Work Duration - 3 months (Crossings to take 2 weeks each including patchback of asphalt) (Remainder of work on south side of E. Tanque Verde Rd. to take 2 months)
-Work on south side of E. Tanque Verde Rd. to primarily use shoulder/bike lane closures as shown in TCP, right lane closure to be used only if necessary
-Work crossing from north to south on both the maximum west and east ends of the project to use a combination of a right lane closure then a "football setup" to completes the crossing in a 4-step process (right lane closure for southern east bound lane, "football" for northern east bound lane the median and the southern west bound lane, right lane closure for northern west bound lane)
-Nights/Variable hours of work for major crossing can be accepted in order to comply with COTDOT needs if needed
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 08/13/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 08/13/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 08/13/2025 | TRSP - ROW - Final | Passed |