Permit: TR-UTL-0425-00566
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
3475 S MAGDA AV
Address NEW:
3475 S MAGDA AV
Apply Date:
04/05/2025
Applicant:
Cox Communications
Description:
PRJ290005-1: Cox to pull 154' through existing conduit, trench 12' and bore 59' to install CATV conduit for system tie.
Permit Reviews
Permit Number - TR-UTL-0425-00566
Permit Status: Complete
Permit Description: PRJ290005-1: Cox to pull 154' through existing conduit, trench 12' and bore 59' to install CATV conduit for system tie.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/07/2025 | RIGHT-OF-WAY REVIEW v.1 | 04/14/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0425-00566
Permit Status: Complete
Permit Description: PRJ290005-1: Cox to pull 154' through existing conduit, trench 12' and bore 59' to install CATV conduit for system tie.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 04/11/2025 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 04/11/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 04/11/2025 | NOTE: WORK IS BEHIND 3475 S MAGDA AV - ADDRESS ON PERMIT IS FOR PERMITTING PURPOSES ONLY. |
| 04/14/2025 | Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley. |
| 04/14/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0425-00566
Permit Description: PRJ290005-1: Cox to pull 154' through existing conduit, trench 12' and bore 59' to install CATV conduit for system tie.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/02/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | Spoke with Francisco over the phone | |
| 05/12/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 05/12/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/14/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 05/19/2025 | TRSP - ROW - Final | Passed | Work is complete |