Permit: TR-UTL-0424-00778
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
3460 E GLENN ST
Address NEW:
3460 E GLENN ST
Apply Date:
04/12/2024
Applicant:
Chelsey Bolinger
Description:
KAHNA P.066626A - (job previously approved under the original design TR-UTL-0723-02164) - BORE 1,741' & TRENCH 45' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (13) FIBER SAI CABINET, FLOWER POT, HANDHOLES & PEDESTALS. OVERLASH 2,402' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY
Permit Reviews
Permit Number - TR-UTL-0424-00778
Permit Status: Complete
Permit Description: KAHNA P.066626A - (job previously approved under the original design TR-UTL-0723-02164) - BORE 1,741' & TRENCH 45' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (13) FIBER SAI CABINET, FLOWER POT, HANDHOLES & PEDESTALS. OVERLASH 2,402' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/12/2024 | RIGHT-OF-WAY REVIEW v.1 | 04/19/2024 | REQUIRES RESUBMIT |
| 05/28/2024 | RIGHT-OF-WAY REVIEW v.2 | 05/31/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0424-00778
Permit Status: Complete
Permit Description: KAHNA P.066626A - (job previously approved under the original design TR-UTL-0723-02164) - BORE 1,741' & TRENCH 45' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (13) FIBER SAI CABINET, FLOWER POT, HANDHOLES & PEDESTALS. OVERLASH 2,402' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 04/15/2024 | PAVEMENT MORATORIUM |
| 04/15/2024 | PRE-CON/PAVEMENT/SIDEWALK |
| 04/15/2024 | PROP 411 |
| 04/15/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-0424-00778
Permite Description: KAHNA P.066626A - (job previously approved under the original design TR-UTL-0723-02164) - BORE 1,741' & TRENCH 45' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (13) FIBER SAI CABINET, FLOWER POT, HANDHOLES & PEDESTALS. OVERLASH 2,402' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/05/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | N/A | Re-inspection required | |
| 09/05/2024 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | N/A | Re-inspection required | |
| 09/05/2024 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | N/A | Re-inspection required | |
| 09/05/2024 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Re-inspection required | |
| 09/05/2024 | TRSP - ROW - Final/Close-Out | N/A | Re-inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0424-00778
Permit Description: KAHNA P.066626A - (job previously approved under the original design TR-UTL-0723-02164) - BORE 1,741' & TRENCH 45' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (13) FIBER SAI CABINET, FLOWER POT, HANDHOLES & PEDESTALS. OVERLASH 2,402' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/19/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 09/09/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/07/2025 | TRSP - ROW - Final/Close-Out | Passed |