Permit: TR-UTL-0424-00743
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
3526 E PRESIDIO RD
Address NEW:
3526 E PRESIDIO RD
Apply Date:
04/09/2024
Applicant:
Chelsey Bolinger
Description:
P.066643B (KAHNA) - (job previously approved under the original design TR-UTL-0723-02157) -BORE 1,947' & TRENCH 2,360' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) CABINET, HANDHOLE, PEDESTAL, FLOWERPOT. OVERLASH 2,232' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY Updated 7/18/2024 - Renewal/Extension. Request for 90 day extension as of 7/25/2024 .
Permit Reviews
Permit Number - TR-UTL-0424-00743
Permit Status: Complete
Permit Description: P.066643B (KAHNA) - (job previously approved under the original design TR-UTL-0723-02157) -BORE 1,947' & TRENCH 2,360' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) CABINET, HANDHOLE, PEDESTAL, FLOWERPOT. OVERLASH 2,232' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY
Updated 7/18/2024 - Renewal/Extension.
Request for 90 day extension as of 7/25/2024 .
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/10/2024 | RIGHT-OF-WAY REVIEW v.1 | 04/18/2024 | REQUIRES RESUBMIT |
| 04/24/2024 | RIGHT-OF-WAY REVIEW v.2 | 04/24/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0424-00743
Permit Status: Complete
Permit Description: P.066643B (KAHNA) - (job previously approved under the original design TR-UTL-0723-02157) -BORE 1,947' & TRENCH 2,360' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) CABINET, HANDHOLE, PEDESTAL, FLOWERPOT. OVERLASH 2,232' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY
Updated 7/18/2024 - Renewal/Extension.
Request for 90 day extension as of 7/25/2024 .
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 04/10/2024 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 04/10/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-0424-00743
Permite Description: P.066643B (KAHNA) - (job previously approved under the original design TR-UTL-0723-02157) -BORE 1,947' & TRENCH 2,360' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) CABINET, HANDHOLE, PEDESTAL, FLOWERPOT. OVERLASH 2,232' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY
Updated 7/18/2024 - Renewal/Extension.
Request for 90 day extension as of 7/25/2024 .
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/24/2024 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Partial Pass | |
| 10/24/2024 | TRSP - ROW - Barricade Takedown | N/A | Re-inspection required | |
| 10/24/2024 | TRSP - ROW - Notice of Completion | N/A | Re-inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0424-00743
Permit Description: P.066643B (KAHNA) - (job previously approved under the original design TR-UTL-0723-02157) -BORE 1,947' & TRENCH 2,360' TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (15) CABINET, HANDHOLE, PEDESTAL, FLOWERPOT. OVERLASH 2,232' OF AERIAL FIBER CABLE. PLACE (1) ANCHOR/DOWN GUY
Updated 7/18/2024 - Renewal/Extension.
Request for 90 day extension as of 7/25/2024 .
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 10/24/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 10/24/2024 | TRSP - ROW - AERIAL INSTALLATION | Passed | ||
| 04/29/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 04/29/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 04/29/2025 | TRSP - ROW - Notice of Completion | Passed |