Permit: TR-UTL-0326-00546
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
4502 S 12TH AV
Address NEW:
4502 S 12TH AV
Apply Date:
03/19/2026
Applicant:
Ben Lozano / Border Traffic Safety LLC
Description:
Fire Hydrant Repair
Permit Reviews
Permit Number - TR-UTL-0326-00546
Permit Status: Complete
Permit Description: Fire Hydrant Repair
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/19/2026 | RIGHT-OF-WAY REVIEW v.1 | 04/02/2026 | REQUIRES RESUBMIT |
| 04/02/2026 | RIGHT-OF-WAY REVIEW v.2 | 04/06/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0326-00546
Permit Status: Complete
Permit Description: Fire Hydrant Repair
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 03/24/2026 | Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination. |
| 03/24/2026 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 03/24/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 04/06/2026 | - All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |
| 04/06/2026 | A designated school zone is located within or adjacent to the project limits. All work activities, lane closures, and traffic control shall be scheduled to avoid school arrival and dismissal times. The contractor shall always maintain safe and continuous pedestrian access. |
| 04/06/2026 | Continuous ADA-compliant pedestrian access shall be maintained at all times. If sidewalks are closed, an approved temporary pedestrian access route shall be provided in accordance with the Manual on Uniform Traffic Control Devices. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0326-00546
Permit Description: Fire Hydrant Repair
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/18/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 05/18/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 05/18/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/18/2026 | TRSP - ROW - Final | Passed |