Permit: TR-UTL-0326-00506
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
3801 N 1ST AV
Address NEW:
3801 N 1ST AV
Apply Date:
03/11/2026
Applicant:
ANGEL MORALES
Description:
P.348377A BORE 90' AND TRENCH 16' TO PLACE CONDUIT AND FIBER CABLE PULL 523' OF FIBER CABLE THROUGH EXISTING CONDUIT PLACE 2870' OF AERIAL FIBER CABLE 04/13/26-Revision was send for TCP and design.
Permit Reviews
Permit Number - TR-UTL-0326-00506
Permit Status: Inspections
Permit Description: P.348377A
BORE 90' AND TRENCH 16' TO PLACE CONDUIT AND FIBER CABLE
PULL 523' OF FIBER CABLE THROUGH EXISTING CONDUIT
PLACE 2870' OF AERIAL FIBER CABLE
04/13/26-Revision was send for TCP and design.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/18/2026 | RIGHT-OF-WAY REVIEW v.2 | 03/25/2026 | APPROVED |
| 04/13/2026 | RIGHT-OF-WAY REVIEW REVISION v.1 | 04/14/2026 | APPROVED |
| 03/12/2026 | RIGHT-OF-WAY REVIEW v.1 | N/A | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0326-00506
Permit Status: Inspections
Permit Description: P.348377A
BORE 90' AND TRENCH 16' TO PLACE CONDUIT AND FIBER CABLE
PULL 523' OF FIBER CABLE THROUGH EXISTING CONDUIT
PLACE 2870' OF AERIAL FIBER CABLE
04/13/26-Revision was send for TCP and design.
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 03/13/2026 | Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination. |
| 03/13/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 03/13/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 03/25/2026 | - Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk. |
| 03/25/2026 | All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |
| 03/25/2026 | Flaggers shall not be stationed within 200 feet of any arterial or collector roadway, or within 200 feet of a signalized intersection |
| 03/25/2026 | The contractor shall always maintain safe and continuous access to all adjacent businesses during construction. |
| 03/25/2026 | The contractor shall restore all disturbed pavement in accordance with the City of Tucson Standard Specifications for Public Improvements and applicable standard details. All pavement patches shall match the existing pavement section and surface condition. The contractor shall maintain all temporary patches in a safe and drivable condition until permanent restoration is completed. Any settlement, cracking, or pavement failure within the patched area shall be repaired by the contractor at no cost to the City for the duration of the warranty period |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0326-00506
Permite Description: P.348377A
BORE 90' AND TRENCH 16' TO PLACE CONDUIT AND FIBER CABLE
PULL 523' OF FIBER CABLE THROUGH EXISTING CONDUIT
PLACE 2870' OF AERIAL FIBER CABLE
04/13/26-Revision was send for TCP and design.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/26/2026 | TRSP - ROW - Barricade - Setup/Routine | N/A | Re-inspection required | Work has not started contractor wishes to extend Precon has not been held |
| 06/26/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | N/A | Re-inspection required | Work has not started contractor wishes to extend Precon has not been held |
| 06/26/2026 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Re-inspection required | Work has not started contractor wishes to extend Precon has not been held |
| 06/26/2026 | TRSP - ROW - Final | N/A | Re-inspection required | Work has not started contractor wishes to extend Precon has not been held |