Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address NEW:
6475 E GOLF LINKS RD
Apply Date:
03/10/2026
Applicant:
Cox Communications
Description:
PRJ311474-1: Cox to overlash 646' of aerial strand & trench 11' to install new CATV conduit for system tie.

Permit Reviews

Permit Number - TR-UTL-0326-00491
Permit Status: Complete
Permit Description: PRJ311474-1: Cox to overlash 646' of aerial strand & trench 11' to install new CATV conduit for system tie.
Start Date Submittal Complete Date Status  
03/11/2026 RIGHT-OF-WAY REVIEW v.1 03/13/2026 REQUIRES RESUBMIT Review Details
03/19/2026 RIGHT-OF-WAY REVIEW v.2 03/26/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0326-00491
Permit Status: Complete
Permit Description: PRJ311474-1: Cox to overlash 646' of aerial strand & trench 11' to install new CATV conduit for system tie.
Total Outstanding Activity Conditions - 7
Date Name
03/12/2026 Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination.
03/12/2026 ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14
03/12/2026 Traffic control set-up approved between 9AM - 3:30PM
03/13/2026 HAWK crossing shall remain open at all times
03/26/2026 All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety
03/26/2026 Field Adjustment Authority Condition - The City reserves the right to modify or require adjustments to the traffic control plan in the field if conditions are determined to be unsafe or causing unnecessary traffic impacts.
03/26/2026 Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk.

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0326-00491
Permit Description: PRJ311474-1: Cox to overlash 646' of aerial strand & trench 11' to install new CATV conduit for system tie.
Total Completed Inspections - 4
Date Description Inspector Results Comments
04/22/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed on site meeting with traffic control, utility, and aerial contractor, next inspection will be barricade set up Monday morning
08/03/2026 TRSP - ROW - Barricade - Setup/Routine Passed all devices removed from site
08/03/2026 TRSP - ROW - Backfill - Placement/Compaction Passed alleyway landscape backfill has been completed
08/03/2026 TRSP - ROW - Final Passed all previous inspections completed, site is clear of debris and devices, approved