Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
101 N 6TH AV
Address NEW:
101 N 6TH AV
Apply Date:
03/24/2025
Applicant:
Adrien Pineda
Description:
ARIZONA PIPELINE WILL NEED TO EXCAVATE (1)10'FTX2'FT TRENCH AND (1)5'FTX5'FT BELL HOLE OVER EXISTING GAS LINE IN ORDER TO REPLACE GAS SERVICE FOR 101 N 6TH AVE

Permit Reviews

Permit Number - TR-UTL-0325-00499
Permit Status: Complete
Permit Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE (1)10'FTX2'FT TRENCH AND (1)5'FTX5'FT BELL HOLE OVER EXISTING GAS LINE IN ORDER TO REPLACE GAS SERVICE FOR 101 N 6TH AVE
Start Date Submittal Complete Date Status  
03/25/2025 RIGHT-OF-WAY REVIEW v.1 04/28/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0325-00499
Permit Status: Complete
Permit Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE (1)10'FTX2'FT TRENCH AND (1)5'FTX5'FT BELL HOLE OVER EXISTING GAS LINE IN ORDER TO REPLACE GAS SERVICE FOR 101 N 6TH AVE
Total Outstanding Activity Conditions - 6
Date Name
03/26/2025 This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Historic Preservation Office at PDSDHistoric@tucsonaz.gov.
03/26/2025 ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D.
03/26/2025 Traffic control set-up approved between 9AM - 3:30PM
03/27/2025 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
03/27/2025 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
03/27/2025 Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0325-00499
Permit Description: ARIZONA PIPELINE WILL NEED TO EXCAVATE (1)10'FTX2'FT TRENCH AND (1)5'FTX5'FT BELL HOLE OVER EXISTING GAS LINE IN ORDER TO REPLACE GAS SERVICE FOR 101 N 6TH AVE
Total Completed Inspections - 4
Date Description Inspector Results Comments
05/05/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
06/30/2025 TRSP - ROW - Barricade - Setup/Routine Passed
06/30/2025 TRSP - ROW - Backfill - Placement/Compaction Passed
09/10/2025 TRSP - ROW - Final Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
101 N 6TH AVE TCP_V1.PDF DOCUMENTS VIEW
101 N 6TH AVE_V1.PDF DOCUMENTS VIEW