Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
3653 E 2ND ST
Address NEW:
3653 E 2ND ST
Apply Date:
03/19/2025
Applicant:
Cox Communications
Description:
PRJ288791-1: Cox to overlash 1007' to existing strand, trench 4' and bore 186' to install CATV conduit for system tie.

Permit Reviews

Permit Number - TR-UTL-0325-00468
Permit Status: Complete
Permit Description: PRJ288791-1: Cox to overlash 1007' to existing strand, trench 4' and bore 186' to install CATV conduit for system tie.
Start Date Submittal Complete Date Status  
03/21/2025 RIGHT-OF-WAY REVIEW v.1 03/26/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0325-00468
Permit Status: Complete
Permit Description: PRJ288791-1: Cox to overlash 1007' to existing strand, trench 4' and bore 186' to install CATV conduit for system tie.
Total Outstanding Activity Conditions - 4
Date Name
03/25/2025 Traffic Control set-up approved between 7AM - 5PM
03/26/2025 PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL.
03/26/2025 Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.
03/26/2025 PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS IF LOCATED WITHIN 660' OF CLOSURE. PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED IF NO ADA RAMPS ACCESSABLE.

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0325-00468
Permit Description: PRJ288791-1: Cox to overlash 1007' to existing strand, trench 4' and bore 186' to install CATV conduit for system tie.
Total Completed Inspections - 6
Date Description Inspector Results Comments
04/23/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
05/14/2025 TRSP - ROW - Barricade - Setup/Routine Passed
05/14/2025 TRSP - ROW - AERIAL INSTALLATION Passed
06/26/2025 TRSP - ROW - Paving - Subgrade/removal/placement Passed
06/26/2025 TRSP - ROW - Barricade Takedown Passed
07/01/2025 TRSP - ROW - Final Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
PRJ288791-1_TCP_V1.PDF DOCUMENTS VIEW
PRJ288791-1_TUCSON_V1.PDF DOCUMENTS VIEW