Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
7450 E STELLA RD
Address NEW:
7450 E STELLA RD
Apply Date:
03/13/2025
Applicant:
Think Safety Inc
Description:
Cox to Overlash 48CT Fiber to existing strand FOR 1390FT Riser down and continue Pulling 170' of fiber through existing conduit on private

Permit Reviews

Permit Number - TR-UTL-0325-00433
Permit Status: Complete
Permit Description: Cox to Overlash 48CT Fiber to existing strand FOR 1390FT Riser down and continue Pulling 170' of fiber through existing conduit on private
Start Date Submittal Complete Date Status  
03/14/2025 RIGHT-OF-WAY REVIEW v.1 03/19/2025 REQUIRES RESUBMIT Review Details
03/31/2025 RIGHT-OF-WAY REVIEW v.2 04/01/2025 REQUIRES RESUBMIT Review Details
04/09/2025 RIGHT-OF-WAY REVIEW v.3 04/10/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0325-00433
Permit Status: Complete
Permit Description: Cox to Overlash 48CT Fiber to existing strand FOR 1390FT Riser down and continue Pulling 170' of fiber through existing conduit on private
Total Outstanding Activity Conditions - 3
Date Name
03/18/2025 Traffic control set-up approved between 9AM - 3:30PM
03/18/2025 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
04/09/2025 Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0325-00433
Permit Description: Cox to Overlash 48CT Fiber to existing strand FOR 1390FT Riser down and continue Pulling 170' of fiber through existing conduit on private
Total Completed Inspections - 5
Date Description Inspector Results Comments
04/23/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed Spoke with Francisco over the phone. He stated he was lining out for blue stakes today and that work would start sometime next week.
04/24/2025 TRSP - ROW - Barricade - Setup/Routine Passed The TCP is being followed
05/02/2025 TRSP - ROW - Final Passed Work is complete
05/02/2025 TRSP - ROW - Barricade Takedown Passed Work is complete
05/02/2025 TRSP - ROW - AERIAL INSTALLATION Passed Work complete

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
PRJ289951-1_TCP_REV 2_V3.PDF DOCUMENTS VIEW
PRJ289951-1_TUCSON_V1.PDF DOCUMENTS VIEW