Permit: TR-UTL-0324-00545
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
2619 N RICHEY BL
Address NEW:
2619 N RICHEY BL
Apply Date:
03/20/2024
Applicant:
Chelsey Bolinger
Description:
KAHNA P.066624C - (job previously approved under the original design TR-UTL-0823-02179) - TRENCH 35' TO PLACE CTL CONDUIT AND FIBER CABLE; PLACE (6) HANDHOLES/PEDESTALS/FLOWER POTS & PLACE (4) ANCHOR/DOWNGUYS
Permit Reviews
Permit Number - TR-UTL-0324-00545
Permit Status: Complete
Permit Description: KAHNA P.066624C - (job previously approved under the original design TR-UTL-0823-02179) - TRENCH 35' TO PLACE CTL CONDUIT AND FIBER CABLE; PLACE (6) HANDHOLES/PEDESTALS/FLOWER POTS & PLACE (4) ANCHOR/DOWNGUYS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/20/2024 | RIGHT-OF-WAY REVIEW v.1 | 03/22/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0324-00545
Permit Status: Complete
Permit Description: KAHNA P.066624C - (job previously approved under the original design TR-UTL-0823-02179) - TRENCH 35' TO PLACE CTL CONDUIT AND FIBER CABLE; PLACE (6) HANDHOLES/PEDESTALS/FLOWER POTS & PLACE (4) ANCHOR/DOWNGUYS
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 03/20/2024 | Traffic Control set-up approved between 7AM - 5PM |
| 03/20/2024 | Pavement Patch type Shall Be in conformance to the current edition of the City of Tucson Public Utility Administrative Manual. |
| 03/20/2024 | PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0324-00545
Permit Description: KAHNA P.066624C - (job previously approved under the original design TR-UTL-0823-02179) - TRENCH 35' TO PLACE CTL CONDUIT AND FIBER CABLE; PLACE (6) HANDHOLES/PEDESTALS/FLOWER POTS & PLACE (4) ANCHOR/DOWNGUYS
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/08/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 08/26/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 08/26/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
| 08/26/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 08/26/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 08/26/2024 | TRSP - ROW - AERIAL INSTALLATION | Passed |