Permit: TR-UTL-0323-01014
Permit Details
Apply Date:
03/06/2023
Applicant:
Doone Baker
Description:
Installing new underground cable and fiber for a total of 5,088'. Phase 4 of 5
Permit Reviews
Permit Number - TR-UTL-0323-01014
Permit Status: Issued
Permit Description: Installing new underground cable and fiber for a total of 5,088'. Phase 4 of 5
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/22/2023 | RIGHT-OF-WAY REVIEW v.1 | 04/18/2023 | APPROVED |
Conditions
Permit Number - TR-UTL-0323-01014
Permit Status: Issued
Permit Description: Installing new underground cable and fiber for a total of 5,088'. Phase 4 of 5
Date | Description | Comments |
---|---|---|
04/18/2023 | This project is within a floodplain. Completion of a Floodplain Use Permit (FUP) is required PRIOR TO ISSUANCE of this permit. | |
04/18/2023 | Land survey required. | |
03/27/2023 | Sun Tran | |
03/27/2023 | Traffic control set-up approved between 9AM - 3:30PM | |
03/27/2023 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TR-UTL-0323-01014
Permite Description: Installing new underground cable and fiber for a total of 5,088'. Phase 4 of 5
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/31/2023 | TRSP - ROW - SITE INSPECTION | N/A | Complete (Recurring) | |
07/14/2023 | TRSP - ROW - Recurring | N/A | Not Ready | |
02/14/2024 | TRSP - ROW - Field Change Request | N/A | Complete (Recurring) |
Completed Inspections
Permit Status: Issued
Permit Number: TR-UTL-0323-01014
Permit Description: Installing new underground cable and fiber for a total of 5,088'. Phase 4 of 5
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/01/2023 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
04/18/2024 | TRSP - ROW - Final/Close-Out | Passed |