Permit: TR-UTL-0226-00417
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
5755 E 22ND ST
Address NEW:
5755 E 22ND ST
Apply Date:
02/27/2026
Applicant:
Description:
wo3197610 5755 e 22nd st 14 14 13 sw replace hydrant bollard in front of address in the dirt easement at the south side of the lot 4LF/sc
Permit Reviews
Permit Number - TR-UTL-0226-00417
Permit Status: Complete
Permit Description: wo3197610 5755 e 22nd st 14 14 13 sw replace hydrant bollard in front of address in the dirt easement at the south side of the lot 4LF/sc
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/02/2026 | RIGHT-OF-WAY REVIEW v.1 | 03/11/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0226-00417
Permit Status: Complete
Permit Description: wo3197610 5755 e 22nd st 14 14 13 sw replace hydrant bollard in front of address in the dirt easement at the south side of the lot 4LF/sc
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 03/04/2026 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 03/04/2026 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0226-00417
Permit Description: wo3197610 5755 e 22nd st 14 14 13 sw replace hydrant bollard in front of address in the dirt easement at the south side of the lot 4LF/sc
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/09/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 04/09/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 04/09/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 04/09/2026 | TRSP - ROW - Final | Passed |