Permit: TR-UTL-0226-00412
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
630 N ALVERNON WY
Address NEW:
630 N ALVERNON WY
Apply Date:
02/27/2026
Applicant:
Angeline Trejo
Description:
C.3098125 - ACCESS EXISTING HH 7211 AND HH 7466 FOR SPLICING Note: Active Prop 101 project on 5th St, Coordination will be required with Hunter Contracting for any work at 5th & Alvernon intersection. Available work window per Hunter is 3/9 - 3/22/26.
Permit Reviews
Permit Number - TR-UTL-0226-00412
Permit Status: Complete
Permit Description: C.3098125 - ACCESS EXISTING HH 7211 AND HH 7466 FOR SPLICING
Note: Active Prop 101 project on 5th St, Coordination will be required with Hunter Contracting for any work at 5th & Alvernon intersection. Available work window per Hunter is 3/9 - 3/22/26.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/05/2026 | RIGHT-OF-WAY REVIEW v.2 | 03/05/2026 | APPROVED |
| 02/27/2026 | RIGHT-OF-WAY REVIEW v.1 | 03/05/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0226-00412
Permit Status: Complete
Permit Description: C.3098125 - ACCESS EXISTING HH 7211 AND HH 7466 FOR SPLICING
Note: Active Prop 101 project on 5th St, Coordination will be required with Hunter Contracting for any work at 5th & Alvernon intersection. Available work window per Hunter is 3/9 - 3/22/26.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 03/03/2026 | Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination. |
| 03/03/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 03/05/2026 | Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign. |
| 03/05/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. - City Prop 101 5th St Restoration |
| 03/05/2026 | Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 03/05/2026 | All work to be perform will require Coordination with City Inspection team and Hunter Contracting |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0226-00412
Permit Description: C.3098125 - ACCESS EXISTING HH 7211 AND HH 7466 FOR SPLICING
Note: Active Prop 101 project on 5th St, Coordination will be required with Hunter Contracting for any work at 5th & Alvernon intersection. Available work window per Hunter is 3/9 - 3/22/26.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/13/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | This inspection is not needed. It is a duplicate inspection, a pre-reactivity meeting was passed by Jeff yesterday. | |
| 04/03/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 04/03/2026 | TRSP - ROW - Final | Passed |