Permit: TR-UTL-0226-00388
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
7148 S 6TH AV
Address NEW:
7148 S 6TH AV
Apply Date:
02/25/2026
Applicant:
Adrien Pineda
Description:
*90 DAYS* ARIZONA PIPELINE CO WILL NEED TO EXCAVATE (1) 5X5 BELL HOLE IN ASPHALT BIKE LANE IN ORDER TO REPLACE GAS SERVICE FOR 7148 S 6TH AV (6th Av Under Pavement Moratorium Condition as of 2/12/2026)
Permit Reviews
Permit Number - TR-UTL-0226-00388
Permit Status: Complete
Permit Description: *90 DAYS*
ARIZONA PIPELINE CO WILL NEED TO EXCAVATE (1) 5X5 BELL HOLE IN ASPHALT BIKE LANE IN ORDER TO REPLACE GAS SERVICE FOR 7148 S 6TH AV (6th Av Under Pavement Moratorium Condition as of 2/12/2026)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/25/2026 | RIGHT-OF-WAY REVIEW v.1 | 03/27/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0226-00388
Permit Status: Complete
Permit Description: *90 DAYS*
ARIZONA PIPELINE CO WILL NEED TO EXCAVATE (1) 5X5 BELL HOLE IN ASPHALT BIKE LANE IN ORDER TO REPLACE GAS SERVICE FOR 7148 S 6TH AV (6th Av Under Pavement Moratorium Condition as of 2/12/2026)
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 03/03/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 03/03/2026 | UNDER A PAVEMENT MORATORIUM, ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
| 03/05/2026 | Condition FPUP Approved and uploaded Floodplain permit will be required prior to work. Within City of Tucson Right of Way. |
| 03/05/2026 | Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0226-00388
Permit Description: *90 DAYS*
ARIZONA PIPELINE CO WILL NEED TO EXCAVATE (1) 5X5 BELL HOLE IN ASPHALT BIKE LANE IN ORDER TO REPLACE GAS SERVICE FOR 7148 S 6TH AV (6th Av Under Pavement Moratorium Condition as of 2/12/2026)
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/22/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 05/28/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 07/08/2026 | TRSP - ROW - Final | Passed |