Permit: TR-UTL-0226-00304
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
2501 W ANKLAM RD
Address NEW:
2501 W ANKLAM RD
Apply Date:
02/16/2026
Applicant:
Esteban Vega - Desert Barricades
Description:
WO'S T124666, T124665, T124844, T127946, T128467, T130302, T115627 - TEP to underground overhead facilities on Anklam from Camino Santiago to Greasewood and facilities on Greasewood to Starr Pass. TEP to install 5 pull boxes, 7 J2 cabinets, 1 single phase transformer, 1 pedestal, 1 switchgear cabinet, 1 – 6” riser. TEP to install 2 – 6” conduits, 4” and 2.5” conduit for distribution facilities. PERMIT TR-UTL-0725-01064 HAS EXPIRED AND WORK STILL ONGOING. FPUP ALREADY DONE UNDER PREVIOUS PERMIT 05/13/26- Renew for 90 days as of 05/17/26 new expiration 08/15/2026 05/07/2026- Denied extension due to no pre-activity meeting was schedule. (emergency work permit)
Permit Reviews
Permit Number - TR-UTL-0226-00304
Permit Status: Inspections
Permit Description: WO'S T124666, T124665, T124844, T127946, T128467, T130302, T115627 - TEP to underground overhead facilities on Anklam from Camino Santiago to Greasewood and facilities on Greasewood to Starr Pass. TEP to install 5 pull boxes, 7 J2 cabinets, 1 single phase transformer, 1 pedestal, 1 switchgear cabinet, 1 – 6” riser. TEP to install 2 – 6” conduits, 4” and 2.5” conduit for distribution facilities. PERMIT TR-UTL-0725-01064 HAS EXPIRED AND WORK STILL ONGOING. FPUP ALREADY DONE UNDER PREVIOUS PERMIT
05/13/26- Renew for 90 days as of 05/17/26 new expiration 08/15/2026
05/07/2026- Denied extension due to no pre-activity meeting was schedule. (emergency work permit)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/17/2026 | RIGHT-OF-WAY REVIEW v.1 | N/A | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0226-00304
Permit Status: Inspections
Permit Description: WO'S T124666, T124665, T124844, T127946, T128467, T130302, T115627 - TEP to underground overhead facilities on Anklam from Camino Santiago to Greasewood and facilities on Greasewood to Starr Pass. TEP to install 5 pull boxes, 7 J2 cabinets, 1 single phase transformer, 1 pedestal, 1 switchgear cabinet, 1 – 6” riser. TEP to install 2 – 6” conduits, 4” and 2.5” conduit for distribution facilities. PERMIT TR-UTL-0725-01064 HAS EXPIRED AND WORK STILL ONGOING. FPUP ALREADY DONE UNDER PREVIOUS PERMIT
05/13/26- Renew for 90 days as of 05/17/26 new expiration 08/15/2026
05/07/2026- Denied extension due to no pre-activity meeting was schedule. (emergency work permit)
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 02/17/2026 | This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Historic Preservation Office at PDSDHistoric@tucsonaz.gov |
| 02/17/2026 | Emergency – After the fact permit – a TCP was not provided due to the nature of the work. Any legal questions related to this work shall be directed to Tucson Electric Power to address since DTM did not have an opportunity to review, approve or inspect work. |
| 02/17/2026 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 02/17/2026 | Traffic control set-up approved between 9AM - 3:30PM |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0226-00304
Permite Description: WO'S T124666, T124665, T124844, T127946, T128467, T130302, T115627 - TEP to underground overhead facilities on Anklam from Camino Santiago to Greasewood and facilities on Greasewood to Starr Pass. TEP to install 5 pull boxes, 7 J2 cabinets, 1 single phase transformer, 1 pedestal, 1 switchgear cabinet, 1 – 6” riser. TEP to install 2 – 6” conduits, 4” and 2.5” conduit for distribution facilities. PERMIT TR-UTL-0725-01064 HAS EXPIRED AND WORK STILL ONGOING. FPUP ALREADY DONE UNDER PREVIOUS PERMIT
05/13/26- Renew for 90 days as of 05/17/26 new expiration 08/15/2026
05/07/2026- Denied extension due to no pre-activity meeting was schedule. (emergency work permit)
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/13/2026 | TRSP - ROW - Final | N/A | Re-inspection required | 2 inch mil and fill, they will be doing a slurry coat over the top of the entire lane after half the lane has been milled reinspection on this. We're using it as a daily. |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0226-00304
Permit Description: WO'S T124666, T124665, T124844, T127946, T128467, T130302, T115627 - TEP to underground overhead facilities on Anklam from Camino Santiago to Greasewood and facilities on Greasewood to Starr Pass. TEP to install 5 pull boxes, 7 J2 cabinets, 1 single phase transformer, 1 pedestal, 1 switchgear cabinet, 1 – 6” riser. TEP to install 2 – 6” conduits, 4” and 2.5” conduit for distribution facilities. PERMIT TR-UTL-0725-01064 HAS EXPIRED AND WORK STILL ONGOING. FPUP ALREADY DONE UNDER PREVIOUS PERMIT
05/13/26- Renew for 90 days as of 05/17/26 new expiration 08/15/2026
05/07/2026- Denied extension due to no pre-activity meeting was schedule. (emergency work permit)
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | See photos and documents upload for full scope of the project. They're waiting on getting materials in. This is a pre-con to update the permit or extend the permit their continuing work with this permit or get a new permit if it's already been extended. |