Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address NEW:
4560 S POINCIANA DR
Apply Date:
02/11/2026
Applicant:
ANGEL MORALES
Description:
P.092922A KAHNA BORE 5021' AND TRENCH 247' TO PLACE CONDUIT AND FIBER CABLE PLACE 8 PEDESTALS AND 28 HAND HOLES

Permit Reviews

Permit Number - TR-UTL-0226-00260
Permit Status: Complete
Permit Description: P.092922A KAHNA BORE 5021' AND TRENCH 247' TO PLACE CONDUIT AND FIBER CABLE PLACE 8 PEDESTALS AND 28 HAND HOLES
Start Date Submittal Complete Date Status  
02/12/2026 RIGHT-OF-WAY REVIEW v.1 02/25/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0226-00260
Permit Status: Complete
Permit Description: P.092922A KAHNA BORE 5021' AND TRENCH 247' TO PLACE CONDUIT AND FIBER CABLE PLACE 8 PEDESTALS AND 28 HAND HOLES
Total Outstanding Activity Conditions - 6
Date Name
02/17/2026 Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvement and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced.
02/17/2026 Traffic Control set-up approved between 7AM - 5PM
02/17/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
02/25/2026 All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety
02/25/2026 The contractor shall coordinate all work activities, including scheduling and traffic control, with the active Southwest Gas (SWG) project currently operating within the same neighborhood to avoid conflicts and ensure public safety
02/25/2026 Work shall be completed prior to January 2027 for repaving project scheduled for Groves neighborhood.

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0226-00260
Permit Description: P.092922A KAHNA BORE 5021' AND TRENCH 247' TO PLACE CONDUIT AND FIBER CABLE PLACE 8 PEDESTALS AND 28 HAND HOLES
Total Completed Inspections - 4
Date Description Inspector Results Comments
06/03/2026 TRSP - ROW - Barricade - Setup/Routine Passed alleyway closures and traffic control devices have been removed, approved
06/03/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed pre-con was held along with other permits A- G
06/03/2026 TRSP - ROW - Backfill - Placement/Compaction Passed landscape areas in alleyways have been backfilled and compacted, approved
06/03/2026 TRSP - ROW - Final Passed all backfill in landscape alleyways has been completed, all traffic control devices removed from site, approved

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
P.092922 AERIAL PERMIT A (02-09-26)_V1.PDF DOCUMENTS VIEW
P.092922 CIVIL PERMIT A (2-9-26)_V1.PDF DOCUMENTS VIEW