Permit: TR-UTL-0226-00200
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
10390 S HOUGHTON RD
Address NEW:
10390 S HOUGHTON RD
Apply Date:
02/02/2026
Applicant:
Antonio Lopez - National Barricade Company
Description:
Water Transmission Main Installation for Tucson Water 04/13/2026 - Request for 30 Day Renewal as of 04/16/2026 05/15/26 – Denied renewal request due to the permit already having a prior extension. 05/26/26-- Denied extension request due to the permit already having a prior approved extension. A new permit application is required. Please include “Continuation of Permit TR-UTL-0226-00200” in the description field when applying. If work is expected to exceed 30 days, permits are available in 30, 60, and 90-day durations. The requested timeframe must be included in both the duration field and the project description when submitting the new application. 05/26/26-Denied revision request due to the permit already being expired. Please apply for a new permit and resubmit all required documents with updated information.
Permit Reviews
Permit Number - TR-UTL-0226-00200
Permit Status: Inspections
Permit Description: Water Transmission Main Installation for Tucson Water
04/13/2026 - Request for 30 Day Renewal as of 04/16/2026
05/15/26 – Denied renewal request due to the permit already having a prior extension.
05/26/26-- Denied extension request due to the permit already having a prior approved extension. A new permit application is required. Please include “Continuation of Permit TR-UTL-0226-00200” in the description field when applying. If work is expected to exceed 30 days, permits are available in 30, 60, and 90-day durations. The requested timeframe must be included in both the duration field and the project description when submitting the new application.
05/26/26-Denied revision request due to the permit already being expired. Please apply for a new permit and resubmit all required documents with updated information.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/17/2026 | RIGHT-OF-WAY REVIEW v.2 | 03/13/2026 | APPROVED |
| 05/22/2026 | RIGHT-OF-WAY REVIEW REVISION v.1 | N/A | REQUIRES RESUBMIT |
| 02/02/2026 | RIGHT-OF-WAY REVIEW v.1 | 02/05/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0226-00200
Permit Status: Inspections
Permit Description: Water Transmission Main Installation for Tucson Water
04/13/2026 - Request for 30 Day Renewal as of 04/16/2026
05/15/26 – Denied renewal request due to the permit already having a prior extension.
05/26/26-- Denied extension request due to the permit already having a prior approved extension. A new permit application is required. Please include “Continuation of Permit TR-UTL-0226-00200” in the description field when applying. If work is expected to exceed 30 days, permits are available in 30, 60, and 90-day durations. The requested timeframe must be included in both the duration field and the project description when submitting the new application.
05/26/26-Denied revision request due to the permit already being expired. Please apply for a new permit and resubmit all required documents with updated information.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 02/04/2026 | ROW Permit is only allowed for work within City of Tucson Right of Way. |
| 02/04/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 02/04/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 02/04/2026 | Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property. |
| 02/18/2026 | Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0226-00200
Permite Description: Water Transmission Main Installation for Tucson Water
04/13/2026 - Request for 30 Day Renewal as of 04/16/2026
05/15/26 – Denied renewal request due to the permit already having a prior extension.
05/26/26-- Denied extension request due to the permit already having a prior approved extension. A new permit application is required. Please include “Continuation of Permit TR-UTL-0226-00200” in the description field when applying. If work is expected to exceed 30 days, permits are available in 30, 60, and 90-day durations. The requested timeframe must be included in both the duration field and the project description when submitting the new application.
05/26/26-Denied revision request due to the permit already being expired. Please apply for a new permit and resubmit all required documents with updated information.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/09/2026 | TRSP - ROW - Barricade - Setup/Routine | N/A | Complete (Recurring) | first phase of traffic control setup is in place. Outer two travel lanes for southbound Houghton are closed. Tapering and advanced warning signs are in place. Contractor is pursuing a 24 hour closure allowance, permit is currently allowing 9 AM to 3 PM work hours. |
| 06/11/2026 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Complete (Recurring) | bedding sand being placed in West shoulder trench, road plates installed for 2 travel lanes on southbound Houghton. |
| 06/11/2026 | TRSP - ROW - Final | N/A | Not Ready | job is still ongoing |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0226-00200
Permit Description: Water Transmission Main Installation for Tucson Water
04/13/2026 - Request for 30 Day Renewal as of 04/16/2026
05/15/26 – Denied renewal request due to the permit already having a prior extension.
05/26/26-- Denied extension request due to the permit already having a prior approved extension. A new permit application is required. Please include “Continuation of Permit TR-UTL-0226-00200” in the description field when applying. If work is expected to exceed 30 days, permits are available in 30, 60, and 90-day durations. The requested timeframe must be included in both the duration field and the project description when submitting the new application.
05/26/26-Denied revision request due to the permit already being expired. Please apply for a new permit and resubmit all required documents with updated information.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/13/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | phone call with Tommy, full traffic control mobilization still one month out, permit will need extension submitted |