Permit: TR-UTL-0225-00353
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
660 W VALENCIA RD
Address NEW:
660 W VALENCIA RD
Apply Date:
02/27/2025
Applicant:
Cox Communications
Description:
PRJ287331-1: Cox to ovelash 287' to existing aerial Strand, trench 15' and Pull 171' through existing CATV conduit for system tie.
Permit Reviews
Permit Number - TR-UTL-0225-00353
Permit Status: Complete
Permit Description: PRJ287331-1: Cox to ovelash 287' to existing aerial Strand, trench 15' and Pull 171' through existing CATV conduit for system tie.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/21/2025 | RIGHT-OF-WAY REVIEW v.3 | 03/21/2025 | APPROVED |
| 02/28/2025 | RIGHT-OF-WAY REVIEW v.1 | 03/05/2025 | REQUIRES RESUBMIT |
| 03/13/2025 | RIGHT-OF-WAY REVIEW v.2 | 03/18/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0225-00353
Permit Status: Complete
Permit Description: PRJ287331-1: Cox to ovelash 287' to existing aerial Strand, trench 15' and Pull 171' through existing CATV conduit for system tie.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 03/04/2025 | BUS STOP/ROUTE |
| 03/04/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 03/04/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 03/17/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0225-00353
Permit Description: PRJ287331-1: Cox to ovelash 287' to existing aerial Strand, trench 15' and Pull 171' through existing CATV conduit for system tie.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/02/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 05/13/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 05/13/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/14/2025 | TRSP - ROW - Final | Passed |