Permit: TR-UTL-0225-00334
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
1735 W SPEEDWAY BL
Address NEW:
1735 W SPEEDWAY BL
Apply Date:
02/25/2025
Applicant:
JUAN PEREZ
Description:
Excavating a 30' x3' trench to abandon gas line service in row in asphalt and dirt. Permit update 4/10/2025: Renewed for 30 days.
Permit Reviews
Permit Number - TR-UTL-0225-00334
Permit Status: Complete
Permit Description: Excavating a 30' x3' trench to abandon gas line service in row in asphalt and dirt.
Permit update 4/10/2025: Renewed for 30 days.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/27/2025 | RIGHT-OF-WAY REVIEW v.1 | 03/03/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0225-00334
Permit Status: Complete
Permit Description: Excavating a 30' x3' trench to abandon gas line service in row in asphalt and dirt.
Permit update 4/10/2025: Renewed for 30 days.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 02/28/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 03/03/2025 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION |
| 03/03/2025 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS IF LOCATED WITHIN 660' OF CLOSURE. PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED IF NO ADA RAMPS ACCESSABLE. |
| 03/03/2025 | PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. |
| 03/03/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 03/03/2025 | Private Property Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0225-00334
Permit Description: Excavating a 30' x3' trench to abandon gas line service in row in asphalt and dirt.
Permit update 4/10/2025: Renewed for 30 days.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/07/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 05/08/2025 | TRSP - ROW - Final | Passed | ||
| 05/02/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 05/02/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed |