Permit: TR-UTL-0225-00303
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
2502 E 21ST ST
Address NEW:
2502 E 21ST ST
Apply Date:
02/19/2025
Applicant:
Kristine Schwartz
Description:
2 5x5 bellholes in drit/blktop front for crews to repair grade 2 gas leak
Permit Reviews
Permit Number - TR-UTL-0225-00303
Permit Status: Complete
Permit Description: 2 5x5 bellholes in drit/blktop front for crews to repair grade 2 gas leak
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/24/2025 | RIGHT-OF-WAY REVIEW v.1 | 02/25/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0225-00303
Permit Status: Complete
Permit Description: 2 5x5 bellholes in drit/blktop front for crews to repair grade 2 gas leak
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 02/25/2025 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvements and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 02/25/2025 | Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley. |
| 02/25/2025 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 02/25/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 02/25/2025 | Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0225-00303
Permit Description: 2 5x5 bellholes in drit/blktop front for crews to repair grade 2 gas leak
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/28/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 04/17/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 04/07/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/01/2025 | TRSP - ROW - Final | Passed |