Permit: TR-UTL-0225-00235
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
2434 S LAYTON PL
Address NEW:
2434 S LAYTON PL
Apply Date:
02/05/2025
Applicant:
Desert Barricades LLC
Description:
WO T112369 - Install (15) Poles, Replace (1) Poles w/ guys & anchors. Install (8) 7/16" Guys & Anchors. Installation of approx. 2,600' of Overhead Conductor (3-477ACSR w/ 4/0 Neutral). (5) Locations with Overhead work Only. Replace (1) Overhead Capacitor. Replace (1) 120/208V-3Ph Transformer Bank. Remove Overhead Conversion Bank(13.8KV-4.16KV). Install (2) Overhead Conversion Banks (13.8KV-4.16KV) Install Overhead Switch.
Permit Reviews
Permit Number - TR-UTL-0225-00235
Permit Status: Complete
Permit Description: WO T112369 - Install (15) Poles, Replace (1) Poles w/ guys & anchors. Install (8) 7/16" Guys & Anchors. Installation of approx. 2,600' of Overhead Conductor (3-477ACSR w/ 4/0 Neutral). (5) Locations with Overhead work Only. Replace (1) Overhead Capacitor. Replace (1) 120/208V-3Ph Transformer Bank. Remove Overhead Conversion Bank(13.8KV-4.16KV).
Install (2) Overhead Conversion Banks (13.8KV-4.16KV) Install Overhead Switch.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/07/2025 | RIGHT-OF-WAY REVIEW v.1 | 02/13/2025 | REQUIRES RESUBMIT |
| 06/02/2025 | RIGHT-OF-WAY REVIEW v.3 | 06/10/2025 | APPROVED |
| 03/05/2025 | RIGHT-OF-WAY REVIEW v.2 | 04/03/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0225-00235
Permit Status: Complete
Permit Description: WO T112369 - Install (15) Poles, Replace (1) Poles w/ guys & anchors. Install (8) 7/16" Guys & Anchors. Installation of approx. 2,600' of Overhead Conductor (3-477ACSR w/ 4/0 Neutral). (5) Locations with Overhead work Only. Replace (1) Overhead Capacitor. Replace (1) 120/208V-3Ph Transformer Bank. Remove Overhead Conversion Bank(13.8KV-4.16KV).
Install (2) Overhead Conversion Banks (13.8KV-4.16KV) Install Overhead Switch.
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 02/10/2025 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
| 02/10/2025 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0225-00235
Permit Description: WO T112369 - Install (15) Poles, Replace (1) Poles w/ guys & anchors. Install (8) 7/16" Guys & Anchors. Installation of approx. 2,600' of Overhead Conductor (3-477ACSR w/ 4/0 Neutral). (5) Locations with Overhead work Only. Replace (1) Overhead Capacitor. Replace (1) 120/208V-3Ph Transformer Bank. Remove Overhead Conversion Bank(13.8KV-4.16KV).
Install (2) Overhead Conversion Banks (13.8KV-4.16KV) Install Overhead Switch.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/04/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | The permit was set to expire, but has received a 90 day renewal/extension. Locates are being refreshed in the area. Work to start soon. | |
| 12/09/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | Traffic control was set up according to the approved TCP | |
| 12/09/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | Backfill around the new pools is sufficient and conforms to PAG standards | |
| 12/16/2025 | TRSP - ROW - Final | Passed | Work is complete |