Permit: TR-UTL-0224-00380
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
4849 E 5TH ST
Address NEW:
4849 E 5TH ST
Apply Date:
02/26/2024
Applicant:
Judy Boyer
Description:
2 5x5 bell holes in blktop/dirt for crews to pothole gas line
Permit Reviews
Permit Number - TR-UTL-0224-00380
Permit Status: Complete
Permit Description: 2 5x5 bell holes in blktop/dirt for crews to pothole gas line
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/28/2024 | RIGHT-OF-WAY REVIEW v.2 | 02/28/2024 | REQUIRES RESUBMIT |
| 02/27/2024 | RIGHT-OF-WAY REVIEW v.1 | 02/27/2024 | REQUIRES RESUBMIT |
| 02/28/2024 | RIGHT-OF-WAY REVIEW v.3 | 02/29/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0224-00380
Permit Status: Complete
Permit Description: 2 5x5 bell holes in blktop/dirt for crews to pothole gas line
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 02/27/2024 | Bus stop/ route |
| 02/27/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0224-00380
Permit Description: 2 5x5 bell holes in blktop/dirt for crews to pothole gas line
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/06/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 03/19/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 03/19/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/08/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | ||
| 05/08/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
| 05/08/2024 | TRSP - ROW - Final/Close-Out | Passed |