Permit: TR-UTL-0224-00378
Permit Details
Apply Date:
02/26/2024
Applicant:
Desert Barricades LLC
Description:
WO'S T25040 & T44621 - TEP to replace poles and equipment related to Voltage Conversion from 4.16KV to 13.8KV. Install (8) Poles, Remove (5) Poles. Relocate (1) Conversion Bank, Replace (9) 1Ph OH Transformers, Replace (2) 3Ph OH Transformer Banks. TEP Contact is Adam Shaw/(520) 334-9568
Permit Reviews
Permit Number - TR-UTL-0224-00378
Permit Status: Complete
Permit Description: WO'S T25040 & T44621 - TEP to replace poles and equipment related to Voltage Conversion from 4.16KV to 13.8KV. Install (8) Poles, Remove (5) Poles. Relocate (1) Conversion Bank, Replace (9) 1Ph OH Transformers, Replace (2) 3Ph OH Transformer Banks. TEP Contact is Adam Shaw/(520) 334-9568
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/26/2024 | RIGHT-OF-WAY REVIEW v.1 | 02/27/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0224-00378
Permit Status: Complete
Permit Description: WO'S T25040 & T44621 - TEP to replace poles and equipment related to Voltage Conversion from 4.16KV to 13.8KV. Install (8) Poles, Remove (5) Poles. Relocate (1) Conversion Bank, Replace (9) 1Ph OH Transformers, Replace (2) 3Ph OH Transformer Banks. TEP Contact is Adam Shaw/(520) 334-9568
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
02/26/2024 | |
02/26/2024 | PAVEMENT MORATORIUM |
02/26/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0224-00378
Permit Description: WO'S T25040 & T44621 - TEP to replace poles and equipment related to Voltage Conversion from 4.16KV to 13.8KV. Install (8) Poles, Remove (5) Poles. Relocate (1) Conversion Bank, Replace (9) 1Ph OH Transformers, Replace (2) 3Ph OH Transformer Banks. TEP Contact is Adam Shaw/(520) 334-9568
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/31/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
05/31/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | ||
05/31/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
05/31/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
07/10/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
05/31/2024 | TRSP - ROW - AERIAL INSTALLATION | Passed | ||
07/09/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |