Permit: TR-UTL-0224-00310
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
4176 N VIA VILLAS
Address NEW:
4176 N VIA VILLAS
Apply Date:
02/13/2024
Applicant:
Andrea Charles
Description:
Trench from existing cabinet to base of pole for 75'. Intercept existing riser and feed new 48ct fiber up then overlash for 4 spans to pole at Via Villas entrance totalling 950' then riser down into exisitng amp ped. Replace amp ped with node ped and install new node in place of amp
Permit Reviews
Permit Number - TR-UTL-0224-00310
Permit Status: Complete
Permit Description: Trench from existing cabinet to base of pole for 75'. Intercept existing riser and feed new 48ct fiber up then overlash for 4 spans to pole at Via Villas entrance totalling 950' then riser down into exisitng amp ped. Replace amp ped with node ped and install new node in place of amp
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/14/2024 | RIGHT-OF-WAY REVIEW v.1 | 02/16/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0224-00310
Permit Status: Complete
Permit Description: Trench from existing cabinet to base of pole for 75'. Intercept existing riser and feed new 48ct fiber up then overlash for 4 spans to pole at Via Villas entrance totalling 950' then riser down into exisitng amp ped. Replace amp ped with node ped and install new node in place of amp
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/14/2024 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0224-00310
Permit Description: Trench from existing cabinet to base of pole for 75'. Intercept existing riser and feed new 48ct fiber up then overlash for 4 spans to pole at Via Villas entrance totalling 950' then riser down into exisitng amp ped. Replace amp ped with node ped and install new node in place of amp
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 05/03/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 05/03/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
| 05/03/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/03/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 05/03/2024 | TRSP - ROW - AERIAL INSTALLATION | Passed |