Permit: TR-UTL-0224-00294
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
2001 E 1ST ST UNIT 2
Address NEW:
2001 E 1ST ST UNIT 2
Apply Date:
02/10/2024
Applicant:
eligio pena
Description:
1 5x5 bell hole in dirt to replace gas at lot # 2
Permit Reviews
Permit Number - TR-UTL-0224-00294
Permit Status: Complete
Permit Description: 1 5x5 bell hole in dirt to replace gas at lot # 2
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/12/2024 | RIGHT-OF-WAY REVIEW v.1 | 02/12/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0224-00294
Permit Status: Complete
Permit Description: 1 5x5 bell hole in dirt to replace gas at lot # 2
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 02/12/2024 | Traffic Control set-up approved between 7AM - 5PM |
| 02/12/2024 | |
| 02/12/2024 | PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-0224-00294
Permite Description: 1 5x5 bell hole in dirt to replace gas at lot # 2
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/12/2024 | TRSP - ROW - Final/Close-Out | N/A | Re-inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0224-00294
Permit Description: 1 5x5 bell hole in dirt to replace gas at lot # 2
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/14/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 03/15/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 03/15/2024 | TRSP - ROW - SWBMP | Passed | ||
| 03/15/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
| 03/15/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 08/06/2024 | TRSP - ROW - Final/Close-Out | Passed |