Permit: TR-UTL-0223-00790
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
2390 N WILMOT RD
Address NEW:
2390 N WILMOT RD
Apply Date:
02/07/2023
Applicant:
Andrea Charles
Description:
Installing new underground cable and fiber for a total of 4,010'. Phase 3 of 5
Permit Reviews
Permit Number - TR-UTL-0223-00790
Permit Status: Complete
Permit Description: Installing new underground cable and fiber for a total of 4,010'. Phase 3 of 5
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/16/2023 | RIGHT-OF-WAY REVIEW v.1 | 02/28/2023 | REQUIRES RESUBMIT |
| 03/14/2023 | RIGHT-OF-WAY REVIEW v.2 | 04/18/2023 | APPROVED |
Conditions
Permit Number - TR-UTL-0223-00790
Permit Status: Complete
Permit Description: Installing new underground cable and fiber for a total of 4,010'. Phase 3 of 5
| Date | Description | Comments |
|---|---|---|
| 04/18/2023 | Land survey required | |
| 02/17/2023 | Sun Tran | |
| 09/26/2023 | TEMPORARY HOLIDAY RESTRICTION | |
| 02/17/2023 | Work Location | |
| 02/17/2023 | Traffic control set-up approved between 9AM - 3:30PM | |
| 02/17/2023 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-0223-00790
Permite Description: Installing new underground cable and fiber for a total of 4,010'. Phase 3 of 5
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/31/2023 | TRSP - ROW - SITE INSPECTION | N/A | Complete (Recurring) |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0223-00790
Permit Description: Installing new underground cable and fiber for a total of 4,010'. Phase 3 of 5
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2023 | TRSP - ROW - Recurring | Passed | ||
| 10/11/2023 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 05/09/2024 | TRSP - ROW - Final/Close-Out | Passed |