Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-UTL-0126-00091
Permit Details
Apply Date:
01/14/2026
Applicant:
Adrien Pineda
Description:
(Approved to apply for ROW Permit by Gloria Salmeron) - Steel Replacement Project - Approx. 6,957 of boring under dirt/pavement/concrete with an approx. 3,467 trench in dirt/pavement/concrete. Crews working in the alleys in the Palo Verde Park neighborhood and crossing Mann Ave and Lehigh Dr w/ alley closure and lane closures.
Permit Reviews
Permit Number - TR-UTL-0126-00091
Permit Status: Issued
Permit Description: (Approved to apply for ROW Permit by Gloria Salmeron)
- Steel Replacement Project -
Approx. 6,957 of boring under dirt/pavement/concrete with an approx. 3,467 trench in dirt/pavement/concrete.
Crews working in the alleys in the Palo Verde Park neighborhood and crossing Mann Ave and Lehigh Dr w/ alley closure and lane closures.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2026 | RIGHT-OF-WAY REVIEW v.1 | 01/29/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0126-00091
Permit Status: Issued
Permit Description: (Approved to apply for ROW Permit by Gloria Salmeron)
- Steel Replacement Project -
Approx. 6,957 of boring under dirt/pavement/concrete with an approx. 3,467 trench in dirt/pavement/concrete.
Crews working in the alleys in the Palo Verde Park neighborhood and crossing Mann Ave and Lehigh Dr w/ alley closure and lane closures.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 01/21/2026 | Alley must be restored to existing or better condition. Alley surface must be graded and compacted to City Standards and Specifications for Public Improvement and existing drainage patterns must be restored and maintained. Any disturbed gravel must be replaced. |
| 01/21/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 01/21/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 01/29/2026 | All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |