Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
4910 N 1ST AV
Address NEW:
4910 N 1ST AV
Apply Date:
01/08/2026
Applicant:
John Rhodes
Description:
03/03/2026- Renew for 90 days as of 03/04/2026 new expiration date 06/02/2026. (ieb) Tie in at existing vault. overpull 360' south across River Rd to new vault. Bore south on 1st Ave 570'. Add 2 vaults and 2 peds. Bore east 300’ next to fire station. Add 1 vault. Bore south 630' on 1st ave. Add 1 vault. Riser up on pole. Bore west on Bromley 260' then bore south 250' into complex. Add 2 vaults Overlash 1910' over 4 spans. Riser down on last pole to the south. Bore west 90' and add 1 vault and ped. Overpull east from 1st ave 1350'. add 7 vaults. Total bore: 2100’. Total Overpull: 1710’. Total Aerial: 1910’.

Permit Reviews

Permit Number - TR-UTL-0126-00060
Permit Status: Inspections
Permit Description: 03/03/2026- Renew for 90 days as of 03/04/2026 new expiration date 06/02/2026. (ieb) Tie in at existing vault. overpull 360' south across River Rd to new vault. Bore south on 1st Ave 570'. Add 2 vaults and 2 peds. Bore east 300’ next to fire station. Add 1 vault. Bore south 630' on 1st ave. Add 1 vault. Riser up on pole. Bore west on Bromley 260' then bore south 250' into complex. Add 2 vaults Overlash 1910' over 4 spans. Riser down on last pole to the south. Bore west 90' and add 1 vault and ped. Overpull east from 1st ave 1350'. add 7 vaults. Total bore: 2100’. Total Overpull: 1710’. Total Aerial: 1910’.
Start Date Submittal Complete Date Status  
01/08/2026 RIGHT-OF-WAY REVIEW v.1 01/12/2026 REQUIRES RESUBMIT Review Details
01/14/2026 RIGHT-OF-WAY REVIEW v.2 01/14/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0126-00060
Permit Status: Inspections
Permit Description: 03/03/2026- Renew for 90 days as of 03/04/2026 new expiration date 06/02/2026. (ieb) Tie in at existing vault. overpull 360' south across River Rd to new vault. Bore south on 1st Ave 570'. Add 2 vaults and 2 peds. Bore east 300’ next to fire station. Add 1 vault. Bore south 630' on 1st ave. Add 1 vault. Riser up on pole. Bore west on Bromley 260' then bore south 250' into complex. Add 2 vaults Overlash 1910' over 4 spans. Riser down on last pole to the south. Bore west 90' and add 1 vault and ped. Overpull east from 1st ave 1350'. add 7 vaults. Total bore: 2100’. Total Overpull: 1710’. Total Aerial: 1910’.
Total Outstanding Activity Conditions - 7
Date Name
01/09/2026 Traffic control set-up approved between 9AM - 3:30PM
01/09/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
01/14/2026 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign
01/14/2026 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. jose.garcia@tucsonaz.gov Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts.
01/14/2026 Message Boards to be place 5 days in advance of work.
01/14/2026 Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14
01/14/2026 Pre-Activity Meeting w/Inspections Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.

Completed Inspections

Permit Status: Inspections
Permit Number: TR-UTL-0126-00060
Permit Description: 03/03/2026- Renew for 90 days as of 03/04/2026 new expiration date 06/02/2026. (ieb) Tie in at existing vault. overpull 360' south across River Rd to new vault. Bore south on 1st Ave 570'. Add 2 vaults and 2 peds. Bore east 300’ next to fire station. Add 1 vault. Bore south 630' on 1st ave. Add 1 vault. Riser up on pole. Bore west on Bromley 260' then bore south 250' into complex. Add 2 vaults Overlash 1910' over 4 spans. Riser down on last pole to the south. Bore west 90' and add 1 vault and ped. Overpull east from 1st ave 1350'. add 7 vaults. Total bore: 2100’. Total Overpull: 1710’. Total Aerial: 1910’.
Total Completed Inspections - 4
Date Description Inspector Results Comments
04/21/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed aerial and underground bore shots going on first northbound lane up to river they have notified the fire department that they are gonna be working around their exit area and the business around the area
06/02/2026 TRSP - ROW - Barricade - Setup/Routine Passed all already completed
06/02/2026 TRSP - ROW - Backfill - Placement/Compaction Passed
06/02/2026 TRSP - ROW - Final Passed all work has been completed on this permit for underground attachments

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
JB0002367700_PERMIT MAP_V1.PDF DOCUMENTS VIEW
TCP_REVISED_CITY OF TUCSON_V2.PDF DOCUMENTS VIEW