Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address NEW:
733 E SPEEDWAY BL
Apply Date:
01/08/2026
Applicant:
Irvin Beltran
Description:
Excavating a 3x2 trench at 733 E SPEEDWAY BLVD in ROW in asphalt and dirt to ABANDON gas service. 2/18/26- 30 DAY RENEWAL AS OF 2/21/26. NEW EXPIRATION OF 3/21/26 3/10/26- REVISION TO TCP

Permit Reviews

Permit Number - TR-UTL-0126-00057
Permit Status: Complete
Permit Description: Excavating a 3x2 trench at 733 E SPEEDWAY BLVD in ROW in asphalt and dirt to ABANDON gas service. 2/18/26- 30 DAY RENEWAL AS OF 2/21/26. NEW EXPIRATION OF 3/21/26 3/10/26- REVISION TO TCP
Start Date Submittal Complete Date Status  
01/08/2026 RIGHT-OF-WAY REVIEW v.1 01/12/2026 REQUIRES RESUBMIT Review Details
03/09/2026 RIGHT-OF-WAY REVIEW REVISION v.1 03/10/2026 APPROVED Review Details
01/13/2026 RIGHT-OF-WAY REVIEW v.2 01/14/2026 REQUIRES RESUBMIT Review Details
01/20/2026 RIGHT-OF-WAY REVIEW v.3 01/20/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0126-00057
Permit Status: Complete
Permit Description: Excavating a 3x2 trench at 733 E SPEEDWAY BLVD in ROW in asphalt and dirt to ABANDON gas service. 2/18/26- 30 DAY RENEWAL AS OF 2/21/26. NEW EXPIRATION OF 3/21/26 3/10/26- REVISION TO TCP
Total Outstanding Activity Conditions - 7
Date Name
01/09/2026 BUS STOP/ROUTE
01/09/2026 PRE-CON/SIDEWALK
01/09/2026 Traffic control set-up approved between 9AM - 3:30PM
01/20/2026 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign.
01/20/2026 PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL
01/20/2026 Private Property Driveways and private property shall NOT be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property.
01/20/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.

Outstanding Inspections

Permit Status: Complete
Permit Number: TR-UTL-0126-00057
Permite Description: Excavating a 3x2 trench at 733 E SPEEDWAY BLVD in ROW in asphalt and dirt to ABANDON gas service. 2/18/26- 30 DAY RENEWAL AS OF 2/21/26. NEW EXPIRATION OF 3/21/26 3/10/26- REVISION TO TCP
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
03/06/2026 TRSP - ROW - Barricade - Setup/Routine N/A Re-inspection required For safety during the set up yes but the barricade set up is not proper. I am having them remove the barricades for the weekend because they're not gonna be back till Tuesday and they do not have a 24 hour set up.

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0126-00057
Permit Description: Excavating a 3x2 trench at 733 E SPEEDWAY BLVD in ROW in asphalt and dirt to ABANDON gas service. 2/18/26- 30 DAY RENEWAL AS OF 2/21/26. NEW EXPIRATION OF 3/21/26 3/10/26- REVISION TO TCP
Total Completed Inspections - 3
Date Description Inspector Results Comments
01/28/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
03/10/2026 TRSP - ROW - Backfill - Placement/Compaction Passed Southwest gas the situation has turned into an emergency repair. They’ve got 24 hour barricades set up. They’re going to have it backfilled and completed tomorrow including the sidewalk panel repair. See photos in the inspection. This is on speedway at 7:33 speedway.
03/18/2026 TRSP - ROW - Final Passed Area has been cleaned up and graded. They are doing work west of this project. The barricades that are set up. Here are not for this permit. Getting ready to close the permit. All work has been completed. All restoration has been completed.

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
733 E SPEEDWAY BLVD - BUS BAY CLOSURE - 26-001 HHC3166 REVISED_V1.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
733 E SPEEDWAY BLVD 1_V1.PDF DOCUMENTS VIEW
733 E SPEEDWAY BLVD UPDATED_V3.PDF DOCUMENTS VIEW