Permit: TR-UTL-0126-00044
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
5602 E 29TH ST
Address NEW:
5602 E 29TH ST
Apply Date:
01/07/2026
Applicant:
ANGEL MORALES
Description:
BORE 3263' & TRENCH 112' TO PLACE CONDUIT AND FIBER CABLE PULL 136' OF FIBER CABLE THROUGH EXISTING CONDUIT PLACE 11 HAND HOLES
Permit Reviews
Permit Number - TR-UTL-0126-00044
Permit Status: Complete
Permit Description: BORE 3263' & TRENCH 112' TO PLACE CONDUIT AND FIBER CABLE
PULL 136' OF FIBER CABLE THROUGH EXISTING CONDUIT
PLACE 11 HAND HOLES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/07/2026 | RIGHT-OF-WAY REVIEW v.1 | 01/12/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0126-00044
Permit Status: Complete
Permit Description: BORE 3263' & TRENCH 112' TO PLACE CONDUIT AND FIBER CABLE
PULL 136' OF FIBER CABLE THROUGH EXISTING CONDUIT
PLACE 11 HAND HOLES
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 01/12/2026 | Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley. |
| 01/12/2026 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 01/12/2026 | Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign. |
| 01/12/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 01/12/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0126-00044
Permit Description: BORE 3263' & TRENCH 112' TO PLACE CONDUIT AND FIBER CABLE
PULL 136' OF FIBER CABLE THROUGH EXISTING CONDUIT
PLACE 11 HAND HOLES
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/04/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | I met on-site with Thomas from Pauley as well as two gentlemen from Lumen. Work will begin within the next few days. Thomas will contact me when traffic control is set up. | |
| 02/11/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | Currently, traffic control has been moved to the side of the road but I inspected it earlier when it was in place and it followed the approved traffic control plan | |
| 04/29/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | New alleyway pull boxes backfilled fully and compacted | |
| 04/29/2026 | TRSP - ROW - Final | Passed | all previous inspections completed, traffic control devices removed from site, approved |