Permit: TR-UTL-0125-00166
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
10301 E EDNA PL
Address NEW:
10301 E EDNA PL
Apply Date:
01/27/2025
Applicant:
Andrea Charles
Description:
Renew in 90 days as of 05/29/2025 new expiration date 08/27/2025 --90 DAY PERMIT EXTENSION REQUESTED, JOB WAS DELAYED-- N.795915 - 1 : ( PAGES 3-8 OF DESIGN PLAN) HOUGHTON FROM E EDNA PL (SOUTH OF 22ND ST) SOUTH TO E FALCON POINT DR (SOUTH OF GOLF LINKS). BORE /TRENCH 5,280 ' , DIG PITS, ADJUST MH TO GRADE, PLACE NEW HHS/MHS/TRAC CLOSURES, & REMOVE/REPLACE ASPHALT. CAPITAL IMPROVEMENT PROJECT Manager - Kyle Dewitte This permit applications' civil plans have been reviewed and approved by PSOMAS engineering - per the City’s requirement.
Permit Reviews
Permit Number - TR-UTL-0125-00166
Permit Status: Inspections
Permit Description: Renew in 90 days as of 05/29/2025 new expiration date 08/27/2025
--90 DAY PERMIT EXTENSION REQUESTED, JOB WAS DELAYED--
N.795915 - 1 : ( PAGES 3-8 OF DESIGN PLAN) HOUGHTON FROM E EDNA PL (SOUTH OF 22ND ST) SOUTH TO E FALCON POINT DR (SOUTH OF GOLF LINKS).
BORE /TRENCH 5,280 ' , DIG PITS, ADJUST MH TO GRADE, PLACE NEW HHS/MHS/TRAC CLOSURES, & REMOVE/REPLACE ASPHALT.
CAPITAL IMPROVEMENT PROJECT Manager - Kyle Dewitte
This permit applications' civil plans have been reviewed and approved by PSOMAS engineering - per the City’s requirement.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/18/2025 | RIGHT-OF-WAY REVIEW v.2 | 02/20/2025 | APPROVED |
| 01/27/2025 | RIGHT-OF-WAY REVIEW v.1 | 02/14/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0125-00166
Permit Status: Inspections
Permit Description: Renew in 90 days as of 05/29/2025 new expiration date 08/27/2025
--90 DAY PERMIT EXTENSION REQUESTED, JOB WAS DELAYED--
N.795915 - 1 : ( PAGES 3-8 OF DESIGN PLAN) HOUGHTON FROM E EDNA PL (SOUTH OF 22ND ST) SOUTH TO E FALCON POINT DR (SOUTH OF GOLF LINKS).
BORE /TRENCH 5,280 ' , DIG PITS, ADJUST MH TO GRADE, PLACE NEW HHS/MHS/TRAC CLOSURES, & REMOVE/REPLACE ASPHALT.
CAPITAL IMPROVEMENT PROJECT Manager - Kyle Dewitte
This permit applications' civil plans have been reviewed and approved by PSOMAS engineering - per the City’s requirement.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 01/30/2025 | Multiple jurisdictions/ IGA |
| 01/30/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 01/30/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 01/30/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0125-00166
Permite Description: Renew in 90 days as of 05/29/2025 new expiration date 08/27/2025
--90 DAY PERMIT EXTENSION REQUESTED, JOB WAS DELAYED--
N.795915 - 1 : ( PAGES 3-8 OF DESIGN PLAN) HOUGHTON FROM E EDNA PL (SOUTH OF 22ND ST) SOUTH TO E FALCON POINT DR (SOUTH OF GOLF LINKS).
BORE /TRENCH 5,280 ' , DIG PITS, ADJUST MH TO GRADE, PLACE NEW HHS/MHS/TRAC CLOSURES, & REMOVE/REPLACE ASPHALT.
CAPITAL IMPROVEMENT PROJECT Manager - Kyle Dewitte
This permit applications' civil plans have been reviewed and approved by PSOMAS engineering - per the City’s requirement.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/29/2025 | TRSP - ROW - Barricade - Setup/Routine | N/A | Not Ready | Project has been delayed. The permit has been extended for 90 days. Waiting for work to begin. |
| 05/29/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | N/A | Not Ready | Project has been delayed. The permit has been extended for 90 days. Waiting for work to begin. |
| 05/29/2025 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Not Ready | Project has been delayed. The permit has been extended for 90 days. Waiting for work to begin. |
| 05/29/2025 | TRSP - ROW - Final | N/A | Not Ready | Project has been delayed. The permit has been extended for 90 days. Waiting for work to begin. |