Permit: TR-UTL-0125-00127
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
3700 S CALLE POLAR
Address NEW:
3700 S CALLE POLAR
Apply Date:
01/21/2025
Applicant:
Cox Communications
Description:
Cox to aerial overlash 4,620', trench 23' and bore 123' to install conduit and place vaulted ped for system tie.
Permit Reviews
Permit Number - TR-UTL-0125-00127
Permit Status: Complete
Permit Description: Cox to aerial overlash 4,620', trench 23' and bore 123' to install conduit and place vaulted ped for system tie.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/22/2025 | RIGHT-OF-WAY REVIEW v.1 | 01/28/2025 | REQUIRES RESUBMIT |
| 02/04/2025 | RIGHT-OF-WAY REVIEW v.2 | 02/05/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0125-00127
Permit Status: Complete
Permit Description: Cox to aerial overlash 4,620', trench 23' and bore 123' to install conduit and place vaulted ped for system tie.
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 01/27/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 01/27/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 01/27/2025 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0125-00127
Permit Description: Cox to aerial overlash 4,620', trench 23' and bore 123' to install conduit and place vaulted ped for system tie.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | phone call with Kevin and Francisco, underground portion to be completed in full tomorrow, aerial work to start next Tuesday through Friday | |
| 02/26/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | trenching route ran from private property to pedestal then northbound to pole riser, backfilled in landscape area using native soil compacted to 85%, approved | |
| 03/05/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | Work is complete. Therefore a traffic control set up inspection is no longer needed. | |
| 03/05/2025 | TRSP - ROW - AERIAL INSTALLATION | Passed | Work is complete | |
| 03/11/2025 | TRSP - ROW - Barricade Takedown | Passed | Traffic control was removed | |
| 03/18/2025 | TRSP - ROW - Final | Passed | Work is done and permit is expired |