Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address NEW:
250 S WILLIAMS BL
Apply Date:
01/21/2025
Applicant:
Adrien Pineda
Description:
ARIZONA PIEPLINE WILL NEED TO EXCAVATE 1 50'X2' TRENCH IN ASPHALT ROW IN ORDER TO REPLACE GAS SERVICE

Permit Reviews

Permit Number - TR-UTL-0125-00122
Permit Status: Complete
Permit Description: ARIZONA PIEPLINE WILL NEED TO EXCAVATE 1 50'X2' TRENCH IN ASPHALT ROW IN ORDER TO REPLACE GAS SERVICE
Start Date Submittal Complete Date Status  
01/22/2025 RIGHT-OF-WAY REVIEW v.1 01/23/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-UTL-0125-00122
Permit Status: Complete
Permit Description: ARIZONA PIEPLINE WILL NEED TO EXCAVATE 1 50'X2' TRENCH IN ASPHALT ROW IN ORDER TO REPLACE GAS SERVICE
Total Outstanding Activity Conditions - 2
Date Name
01/23/2025 ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. .
01/23/2025 Traffic Control set-up approved between 7AM - 5PM

Outstanding Inspections

Permit Status: Complete
Permit Number: TR-UTL-0125-00122
Permite Description: ARIZONA PIEPLINE WILL NEED TO EXCAVATE 1 50'X2' TRENCH IN ASPHALT ROW IN ORDER TO REPLACE GAS SERVICE
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
02/12/2025 TRSP - ROW - Backfill - Placement/Compaction N/A Re-inspection required
03/04/2025 TRSP - ROW - Final N/A Re-inspection required

Completed Inspections

Permit Status: Complete
Permit Number: TR-UTL-0125-00122
Permit Description: ARIZONA PIEPLINE WILL NEED TO EXCAVATE 1 50'X2' TRENCH IN ASPHALT ROW IN ORDER TO REPLACE GAS SERVICE
Total Completed Inspections - 4
Date Description Inspector Results Comments
01/28/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
02/20/2025 TRSP - ROW - Barricade - Setup/Routine Passed
02/25/2025 TRSP - ROW - Backfill - Placement/Compaction Passed
03/14/2025 TRSP - ROW - Final Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
250 S WILLIAMS BLVD AERIAL_V1.PDF DOCUMENTS VIEW
250 S WILLIAMS BLVD SITE_V1.PDF DOCUMENTS VIEW
250 S WILLIAMS BLVD TCP1_V1.PDF DOCUMENTS VIEW
250 S WILLIAMS BLVD TCP2_V1.PDF DOCUMENTS VIEW