Permit: TR-UTL-0125-00113
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
6627 S TUCSON BL
Address NEW:
6627 S TUCSON BL
Apply Date:
01/17/2025
Applicant:
Cox Communications
Description:
PRJ282534-1: Cox to trench 8' and bore 80' to install CATV conduit for system tie.
Permit Reviews
Permit Number - TR-UTL-0125-00113
Permit Status: Complete
Permit Description: PRJ282534-1: Cox to trench 8' and bore 80' to install CATV conduit for system tie.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/21/2025 | RIGHT-OF-WAY REVIEW v.1 | 01/24/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-0125-00113
Permit Status: Complete
Permit Description: PRJ282534-1: Cox to trench 8' and bore 80' to install CATV conduit for system tie.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 01/23/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 01/23/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 01/23/2025 | PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. |
| 01/23/2025 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 01/24/2025 | Driveways and private property shall not be utilized without the owner’s consent. It is the contractor’s responsibility to negotiate use of private property |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-0125-00113
Permit Description: PRJ282534-1: Cox to trench 8' and bore 80' to install CATV conduit for system tie.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 02/14/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 02/14/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 02/26/2025 | TRSP - ROW - SITE INSPECTION | Passed | ||
| 03/25/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 04/02/2025 | TRSP - ROW - Final | Passed |