Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-SWF-0625-00076
Permit Details
Status:
Inspections
Type:
Right-of-Way Small Wireless
Address:
1390 W PASTIME RD
Address NEW:
1390 W PASTIME RD
Apply Date:
06/23/2025
Applicant:
Brad Lowe
Description:
SOW FOR TUC01_010 (14819350) Remove existing antenna and RRHs. Install (1) canister antenna on new mount. Install (1) RRH unit inside (1) RRH cabinet. Install (1) RRH cabinet on concrete slab. Install new 4” conduit for fiber from existing AT&T fiber meet vault to new RRH cabinet – trench approx. 5’-0”. Install new 4” conduit for coax from new RRH cabinet to existing pole – trench approx. 16’-0”. Existing 1.5” conduit for power to be intercepted and ran to new RRH cabinet – trench approx. 20’-0”. Install new 1.5” conduit for power from new RRH cabinet to existing pole – trench approx. 17’-0”.
Permit Reviews
Permit Number - TR-SWF-0625-00076
Permit Status: Inspections
Permit Description: SOW FOR TUC01_010 (14819350)
Remove existing antenna and RRHs. Install (1) canister antenna on new mount. Install (1) RRH unit inside (1) RRH cabinet. Install (1) RRH cabinet on concrete slab. Install new 4” conduit for fiber from existing AT&T fiber meet vault to new RRH cabinet – trench approx. 5’-0”. Install new 4” conduit for coax from new RRH cabinet to existing pole – trench approx. 16’-0”. Existing 1.5” conduit for power to be intercepted and ran to new RRH cabinet – trench approx. 20’-0”. Install new 1.5” conduit for power from new RRH cabinet to existing pole – trench approx. 17’-0”.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/24/2025 | SMALL WIRELESS FACILITIES REVIEW v.1 | 08/12/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-SWF-0625-00076
Permit Status: Inspections
Permit Description: SOW FOR TUC01_010 (14819350)
Remove existing antenna and RRHs. Install (1) canister antenna on new mount. Install (1) RRH unit inside (1) RRH cabinet. Install (1) RRH cabinet on concrete slab. Install new 4” conduit for fiber from existing AT&T fiber meet vault to new RRH cabinet – trench approx. 5’-0”. Install new 4” conduit for coax from new RRH cabinet to existing pole – trench approx. 16’-0”. Existing 1.5” conduit for power to be intercepted and ran to new RRH cabinet – trench approx. 20’-0”. Install new 1.5” conduit for power from new RRH cabinet to existing pole – trench approx. 17’-0”.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 08/07/2025 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 08/07/2025 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST MARKED ADA ACCESS RAMPS IF LOCATED WITHIN 660' OF CLOSURE. PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED IF NO MARKED ADA RAMPS AND CROSSING ACCESSABLE WITHIN 660' OF SIDEWALK CLOSURE. ACCESSABLE. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 08/07/2025 | Pre-Activity Meeting Pre- activity meeting to be held 72 hrs in advance of work start with inspections.. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 08/07/2025 | Your project work requires that you contact the Flowing Wells Unified School District to alert them and coordinate work as needed in school zones. |
| 08/07/2025 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-SWF-0625-00076
Permit Description: SOW FOR TUC01_010 (14819350)
Remove existing antenna and RRHs. Install (1) canister antenna on new mount. Install (1) RRH unit inside (1) RRH cabinet. Install (1) RRH cabinet on concrete slab. Install new 4” conduit for fiber from existing AT&T fiber meet vault to new RRH cabinet – trench approx. 5’-0”. Install new 4” conduit for coax from new RRH cabinet to existing pole – trench approx. 16’-0”. Existing 1.5” conduit for power to be intercepted and ran to new RRH cabinet – trench approx. 20’-0”. Install new 1.5” conduit for power from new RRH cabinet to existing pole – trench approx. 17’-0”.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/06/2025 | TRSP - SWF - Preconstruction Meeting | Passed |